4180 S ARLINGTON AVE 90008

Certificate Information: 4180 S ARLINGTON AVE 90008

Application / Permit
18014-70000-00190
Plan Check / Job No.
B18SL00055
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
Reframe and enlarge (E) detached garage to 19'x18'-3" for (E) SFD
Permit Issued
Issued on 1/29/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 6/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2018 APPLICANT
Assigned to Plan Check Engineer 2/8/2018 ALYSSA N NARCISO
Corrections Issued 2/16/2018 ALYSSA N NARCISO
Quality Review Completed 2/22/2018 SAI KHUM
Building Plans Picked Up 3/2/2018 APPLICANT
Applicant returned to address corrections 2/2/2019 MICHAEL PEREZ
Applicant returned to address corrections 8/13/2019 ALYSSA N NARCISO
Plan Check Approved 9/30/2019 ALYSSA N NARCISO
Issued 1/29/2020 LADBS
CofO in Progress 6/18/2021 DAVID FEILER
Permit Finaled 6/29/2021 DEROLD HAUFF
CofO Issued 6/29/2021 DEROLD HAUFF
Permit Finaled 6/29/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/16/2018 MICHAEL CASTILLO
Green Code Cleared 6/29/2018 NEGAR NEJAD
Low Impact Development Cleared 7/2/2018 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/2/2018 FATIMA GUERRA
Low Impact Development Cleared 6/6/2019 JORGE MEJIA LEMUS
Miscellaneous Cleared 6/6/2019 TERRY PHAN
Green Code Cleared 9/30/2019 ALYSSA N NARCISO

Contact Information

Architect Johnson, David Michael; Lic. No.: C18045 3638 AUREOLA BLVD      LOS ANGELES, CA 90008
Contractor Ram Building & Remodeling Inc; Lic. No.: 929093-B 10423 ATLANTIC AVENUE      SOUTH GATE, CA 90280

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/9/2020 Partial Inspection COREY HUPP
Footing/Foundation/Slab 3/16/2020 Corrections Issued COREY HUPP
Wood Frame 4/13/2020 Partial Approval COREY HUPP
Wood Frame 4/16/2020 Partial Approval COREY HUPP
Footing/Foundation/Slab 6/4/2020 Approved COREY HUPP
Wood Frame 9/9/2020 Partial Approval DONALD CRICHLOW
BUILDING-Rough-Frame 10/26/2020 Partial Approval DONALD CRICHLOW
Green Building Rough 10/26/2020 Approved DONALD CRICHLOW
BUILDING-Rough-Frame 11/5/2020 Not Ready for Inspection DAVID FEILER
Interior/Exterior Lathing 11/5/2020 Corrections Issued DAVID FEILER
Wood Frame 11/5/2020 Not Ready for Inspection DAVID FEILER
Insulation 12/21/2020 Not Ready for Inspection DAVID FEILER
Drywall Nailing 1/8/2021 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 1/8/2021 Not Ready for Inspection STUART CHAPMAN
Shower Pan 1/8/2021 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 2/18/2021 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 4/27/2021 Approved DAVID FEILER
Drywall Nailing 4/27/2021 Approved DAVID FEILER
ELECTRICAL-Final 4/27/2021 Partial Inspection DAVID FEILER
Final 4/27/2021 Not Ready for Inspection DAVID FEILER
Green Building Final 4/27/2021 Approved DAVID FEILER
PLUMBING-Final 4/27/2021 Not Ready for Inspection DAVID FEILER
Smoke Detectors 4/27/2021 Approved DAVID FEILER
ELECTRICAL-Final 5/11/2021 Approved DAVID FEILER
Final 5/11/2021 Partial Inspection DAVID FEILER
HVAC-Final 5/11/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Final 5/11/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 6/7/2021 Approved DAVID FEILER
Final 6/7/2021 OK to Issue CofO DAVID FEILER
HVAC-Final 6/7/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Final 6/7/2021 Not Ready for Inspection DAVID FEILER