366 W OLIVER ST 90731
Certificate Information: 366 W OLIVER ST 90731
- Application / Permit
- 18014-40000-03512
- Plan Check / Job No.
- B18SP00630
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) Second story addition (952 SF) to (E) one-story SFD (1990LA68521) per engineered design and interior remodel to (E) SFD.
- Permit Issued
- Issued on 6/26/2019
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 5/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2018 | APPLICANT |
| Green Plans Picked Up | 7/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2018 | KAVIAN REFAHI |
| Corrections Issued | 8/20/2018 | KAVIAN REFAHI |
| Quality Review Completed | 8/30/2018 | TARIK SAOUD |
| Building Plans Picked Up | 9/13/2018 | APPLICANT |
| Applicant returned to address corrections | 12/19/2018 | KAVIAN REFAHI |
| Plan Check Approved | 1/11/2019 | KAVIAN REFAHI |
| Issued | 6/26/2019 | LADBS |
| CofO in Progress | 12/1/2020 | JOHN KLARIN |
| Permit Finaled | 5/1/2021 | DEROLD HAUFF |
| CofO Issued | 5/1/2021 | DEROLD HAUFF |
| Permit Finaled | 5/1/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 10/11/2018 | STEVEN HOFSTAD |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2018 | MICHAEL CASTILLO |
| Grading Pre-Inspection | Cleared | 10/16/2018 | PATRICK MISCHLICH |
| Project located in CRA area | Cleared | 10/16/2018 | JIM URQUHART |
| Sewer availability | Cleared | 10/16/2018 | MICHAEL CASTILLO |
| Low Impact Development | Cleared | 12/6/2018 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 12/6/2018 | MICHAEL CASTILLO |
| Green Code | Cleared | 12/18/2018 | RICHARD GARCIA |
| GPI Written Notices | Cleared | 1/11/2019 | KAVIAN REFAHI |
Contact Information
| Contractor | R F M General Construction; Lic. No.: 692454-B | 1327 MC DONALD AVENUE WILMINGTON, CA 90744 |
| Engineer | Dixon,, Alexander; Lic. No.: C32963 | 2742 REGWAY AVE LONG BEACH, CA 90810 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/30/2019 | Approved | ANSON MAGLASANG |
| Footing/Foundation/Slab | 8/30/2019 | Approved | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2019 | Partial Approval | ANSON MAGLASANG |
| PLUMBING-Rough | 9/17/2019 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2019 | Corrections Issued | WILLIAM ROSE |
| BUILDING-Rough-Frame | 10/21/2019 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2019 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 10/21/2019 | Not Ready for Inspection | ANSON MAGLASANG |
| MERV13>=Rough | 10/21/2019 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 10/21/2019 | Approved | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2019 | Partial Approval | ANSON MAGLASANG |
| HVAC-Rough | 11/6/2019 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 11/27/2019 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 12/3/2019 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 12/3/2019 | Approved | EUGENE CASSIDY |
| Green Building Rough | 12/3/2019 | Approved | EUGENE CASSIDY |
| MERV13>=Rough | 12/3/2019 | Approved | EUGENE CASSIDY |
| Insulation | 12/16/2019 | Not Ready for Inspection | ANSON MAGLASANG |
| Interior/Exterior Lathing | 12/16/2019 | Approved | ANSON MAGLASANG |
| Insulation | 12/27/2019 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 1/2/2020 | Approved | JOHN KLARIN |
| Final | 4/6/2020 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 4/6/2020 | Approved | JOHN KLARIN |
| MERV13>=Final | 4/6/2020 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 4/6/2020 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 4/6/2020 | Approved | JOHN KLARIN |
| Final | 7/15/2020 | Not Ready for Inspection | JOHN KLARIN |
| Final | 8/3/2020 | Corrections Issued | JOHN KLARIN |
| Final | 11/30/2020 | OK to Issue CofO | JOHN KLARIN |