5225 N LOLETA AVE 90041
Certificate Information: 5225 N LOLETA AVE 90041
- Application / Permit
- 18014-40000-02913
- Plan Check / Job No.
- B18SP00542
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2 story addition at rear and front of (E) SFD
- Permit Issued
- Issued on 10/26/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2018 | KAVIAN REFAHI |
| Corrections Issued | 7/26/2018 | KAVIAN REFAHI |
| Green Plans Picked Up | 7/27/2018 | APPLICANT |
| Quality Review Completed | 8/2/2018 | TARIK SAOUD |
| Building Plans Picked Up | 8/10/2018 | APPLICANT |
| Applicant returned to address corrections | 10/1/2018 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/9/2018 | KAVIAN REFAHI |
| Plan Check Approved | 10/26/2018 | KAVIAN REFAHI |
| Issued | 10/26/2018 | LADBS |
| CofO in Progress | 1/13/2024 | CRAIG VAUGHAN |
| CofO Issued | 1/16/2024 | DEROLD HAUFF |
| Permit Finaled | 1/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2018 | JEANETTE VONG |
| Sewer availability | Cleared | 9/24/2018 | JEANETTE VONG |
| Grading Pre-Inspection | Cleared | 10/1/2018 | PATRICK MISCHLICH |
| Low Impact Development | Cleared | 10/1/2018 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 10/1/2018 | JEANETTE VONG |
| Green Code | Cleared | 10/10/2018 | RICHARD GARCIA |
| GPI Written Notices | Cleared | 10/22/2018 | KAVIAN REFAHI |
Contact Information
| Architect | Kim,, Nam H; Lic. No.: C30825 | 1832 SANTA RENA DRIVE RANCHO PALOS VERDES, CA 90275 |
| Architect | Salcedo, Glen Charles; Lic. No.: C33143 | P O BOX 14202 LOS ANGELES, CA 91406 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/14/2018 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 12/24/2018 | Corrections Issued | RUBEN SALAS |
| PLUMBING-Rough | 12/24/2018 | Corrections Issued | RUBEN SALAS |
| PLUMBING-Rough | 12/27/2018 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2019 | Partial Approval | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2019 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2019 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 8/7/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| Sewer | 8/7/2019 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Rough | 8/13/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| Sewer | 8/13/2019 | Partial Approval | BRIAN SULLIVAN |
| HVAC-Rough | 8/15/2019 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Rough | 8/20/2019 | No Access for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/20/2019 | No Access for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 9/3/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/3/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| Sewer | 9/3/2019 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 9/12/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/12/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| Gas Test | 9/13/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/13/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/19/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 9/19/2019 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2019 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 9/19/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 9/19/2019 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/19/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/27/2019 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 9/27/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 9/27/2019 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/27/2019 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/16/2019 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/16/2019 | Approved | CRAIG VAUGHAN |
| Insulation | 10/25/2019 | Approved | RUBEN SALAS |
| Drywall Nailing | 11/13/2019 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 2/3/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 2/6/2020 | Corrections Issued | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 2/10/2020 | Partial Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 3/11/2020 | Partial Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 3/16/2020 | Partial Inspection | BRIAN SULLIVAN |
| Pre-Inspection | 3/16/2020 | Partial Inspection | BRIAN SULLIVAN |
| Final | 6/11/2020 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/11/2020 | Approved | CRAIG VAUGHAN |
| Green Building Final | 6/11/2020 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 6/11/2020 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 6/11/2020 | Corrections Issued | CRAIG VAUGHAN |
| Final | 6/18/2020 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 6/18/2020 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 6/18/2020 | Approved | CRAIG VAUGHAN |
| Final | 6/26/2020 | OK to Issue CofO | CRAIG VAUGHAN |