1836 W 1ST ST 90732

Certificate Information: 1836 W 1ST ST 90732

Application / Permit
18014-40000-02558
Plan Check / Job No.
B18SP00466
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel, ground floor and rooftop deck addition to existing 1-story single family dwelling.
Permit Issued
Issued on 9/4/2018
Issuing Office
San Pedro
Current Status
CofO Issued on 1/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2018 APPLICANT
Assigned to Plan Check Engineer 5/24/2018 MARJAN SHENASI
Corrections Issued 5/29/2018 MARJAN SHENASI
Quality Review Completed 5/31/2018 JASON HEALEY
Building Plans Picked Up 6/5/2018 APPLICANT
Applicant returned to address corrections 6/11/2018 MARJAN SHENASI
Green Plans Picked Up 6/11/2018 APPLICANT
Applicant returned to address corrections 8/2/2018 MARJAN SHENASI
Applicant returned to address corrections 8/7/2018 MARJAN SHENASI
Applicant returned to address corrections 8/17/2018 MARJAN SHENASI
Applicant returned to address corrections 8/27/2018 MARJAN SHENASI
Plan Check Approved 9/4/2018 MARJAN SHENASI
Issued 9/4/2018 LADBS
CofO in Progress 12/4/2020 JOHN KLARIN
CofO in Progress 12/6/2020 JOHN KLARIN
No Progress 12/8/2020 ANSON MAGLASANG
CofO in Progress 1/4/2021 ANSON MAGLASANG
Permit Finaled 1/4/2021 DEROLD HAUFF
CofO Issued 1/4/2021 DEROLD HAUFF
Permit Finaled 1/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/26/2018 PATRICK MISCHLICH
Low Impact Development Cleared 7/27/2018 SAM NAVID
Green Code Cleared 8/1/2018 RICHARD GARCIA
BHO/Hillside ordinance Cleared 8/2/2018 PHILLIP WILSON
BHO/Hillside ordinance Cleared 8/2/2018 PHILLIP WILSON
BHO/Hillside ordinance Cleared 8/2/2018 PHILLIP WILSON
Eng Process Fee Ord 176,300 Cleared 8/2/2018 PHILLIP WILSON
Roof/Waste drainage to street Cleared 8/2/2018 PHILLIP WILSON
ZA Case Cleared 8/2/2018 SEAN VEAL

Contact Information

Contractor Owner-Builder       ,
Engineer Namvar, Mohammad Alipour; Lic. No.: C39797 231 VISTA DEL MAR STE D      REDONDO BEACH, CA 90277

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/17/2018 Approved ANSON MAGLASANG
Special/Order Compliance 10/17/2018 Corrections Issued ANSON MAGLASANG
BUILDING-Rough-Frame 11/15/2018 Partial Approval ANSON MAGLASANG
Green Building Rough 11/15/2018 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 11/27/2018 Not Ready for Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 12/19/2018 Partial Approval ANSON MAGLASANG
Green Building Rough 12/19/2018 Not Ready for Inspection ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 1/4/2019 Partial Approval ANSON MAGLASANG
ELECTRICAL-Rough 1/24/2019 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 1/24/2019 Not Ready for Inspection ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 1/25/2019 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Rough 1/31/2019 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 1/31/2019 Not Ready for Inspection ANSON MAGLASANG
Pre-Inspection 2/7/2019 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Rough 2/8/2019 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 2/8/2019 Not Ready for Inspection ANSON MAGLASANG
Green Building Rough 2/11/2019 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 2/11/2019 Partial Approval ANSON MAGLASANG
ELECTRICAL-Rough 2/19/2019 Not Ready for Inspection ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 2/19/2019 Not Ready for Inspection ANSON MAGLASANG
Interior/Exterior Lathing 2/19/2019 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 2/19/2019 Not Ready for Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 2/21/2019 Partial Approval ANSON MAGLASANG
Green Building Rough 2/21/2019 Not Ready for Inspection ANSON MAGLASANG
Interior/Exterior Lathing 2/21/2019 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Rough 2/22/2019 Corrections Issued ANSON MAGLASANG
PLUMBING-Rough 2/27/2019 Approved ANSON MAGLASANG
Rough-Elec/Plmb/HVAC 2/27/2019 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 3/1/2019 Approved ANSON MAGLASANG
Green Building Rough 3/1/2019 Approved ANSON MAGLASANG
Interior/Exterior Lathing 3/1/2019 Not Ready for Inspection ANSON MAGLASANG
Drywall Nailing 3/12/2019 Not Ready for Inspection ANSON MAGLASANG
Interior/Exterior Lathing 3/12/2019 Not Ready for Inspection ANSON MAGLASANG
Interior/Exterior Lathing 3/19/2019 Not Ready for Inspection ANSON MAGLASANG
Drywall Nailing 3/26/2019 Approved ANSON MAGLASANG
Insulation 3/26/2019 Approved ANSON MAGLASANG
Drywall Nailing 3/29/2019 Not Ready for Inspection ANSON MAGLASANG
Interior/Exterior Lathing 4/1/2019 Partial Approval ANSON MAGLASANG
Drywall Nailing 4/4/2019 Approved ANSON MAGLASANG
Interior/Exterior Lathing 4/10/2019 Partial Approval ANSON MAGLASANG
Final 6/10/2019 Not Ready for Inspection ANSON MAGLASANG
Green Building Final 6/10/2019 Not Ready for Inspection ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 6/10/2019 SGSOV Not Ready ANSON MAGLASANG
Smoke Detectors 6/10/2019 Not Ready for Inspection ANSON MAGLASANG
Final 3/12/2020 Corrections Issued ANSON MAGLASANG
Green Building Final 3/12/2020 Corrections Issued ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 3/12/2020 SGSOV Not Ready ANSON MAGLASANG
Smoke Detectors 3/12/2020 Not Ready for Inspection ANSON MAGLASANG
Final 8/3/2020 Not Ready for Inspection JOHN KLARIN
Green Building Final 8/3/2020 Conditional Approval JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 8/3/2020 SGSOV Approved JOHN KLARIN
Smoke Detectors 8/3/2020 Approved JOHN KLARIN
Final 8/4/2020 Corrections Issued JOHN KLARIN
Green Building Final 8/4/2020 Approved JOHN KLARIN
Final 9/10/2020 Conditional Approval JOHN KLARIN
Final 11/13/2020 OK to Issue CofO JOHN KLARIN
Special/Order Compliance 12/10/2020 Corrections Issued JOHN KLARIN