6421 W 87TH PL 90045
Certificate Information: 6421 W 87TH PL 90045
- Application / Permit
- 18014-30002-05644
- Plan Check / Job No.
- B20WL02076
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- Supplemental permit to #18014-30000-05644 to change the application type to new detached garage w/. attached storage room and 1/2 bathroom. no change in plot plan
- Permit Issued
- Issued on 9/10/2020
- Issuing Office
- Current Status
- Permit Finaled on 3/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | REZA HAGHIGHAT |
| Corrections Issued | 5/15/2020 | REZA HAGHIGHAT |
| Plan Check Approved | 9/10/2020 | REZA HAGHIGHAT |
| Issued | 9/10/2020 | APPLICANT |
| Permit Finaled | 3/25/2021 | MARIAN PODPORA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/16/2020 | Approved | MARIAN PODPORA |
| Underground Mechanical | 9/16/2020 | Partial Approval | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2020 | Corrections Issued | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Partial Approval | MARIAN PODPORA |
| BUILDING-Rough-Frame | 11/30/2020 | Approved | JOHN MATTILLO |
| ELECTRICAL-Rough | 11/30/2020 | Approved | JOHN MATTILLO |
| Green Building Rough | 11/30/2020 | Approved | JOHN MATTILLO |
| PLUMBING-Rough | 11/30/2020 | Approved | JOHN MATTILLO |
| Sewer | 11/30/2020 | Approved | JOHN MATTILLO |
| Insulation | 12/14/2020 | Approved | JOHN MATTILLO |
| Interior/Exterior Lathing | 12/14/2020 | Approved | JOHN MATTILLO |
| Drywall Nailing | 12/17/2020 | Approved | JOHN MATTILLO |
| ELECTRICAL-Final | 2/19/2021 | Corrections Issued | MARIAN PODPORA |
| Final | 2/19/2021 | Corrections Issued | MARIAN PODPORA |
| Green Building Final | 2/19/2021 | Not Ready for Inspection | MARIAN PODPORA |
| PLUMBING-Final | 2/19/2021 | Approved | MARIAN PODPORA |
| SGSOV-Seismic Gas S/O Valve | 2/19/2021 | SGSOV Not Ready | MARIAN PODPORA |
| Service/Power Release | 2/19/2021 | Approved | MARIAN PODPORA |
| ELECTRICAL-Final | 2/23/2021 | Not Ready for Inspection | MARIAN PODPORA |
| Final | 2/23/2021 | Not Ready for Inspection | MARIAN PODPORA |
| Green Building Final | 2/23/2021 | Approved | MARIAN PODPORA |
| PLUMBING-Final | 2/23/2021 | Not Ready for Inspection | MARIAN PODPORA |
| SGSOV-Seismic Gas S/O Valve | 2/24/2021 | SGSOV Approved | MARIAN PODPORA |
| Final | 3/17/2021 | Conditional Approval | JOHN MATTILLO |
| Final | 3/25/2021 | Permit Finaled | MARIAN PODPORA |