7701 S KITTYHAWK AVE 90045

Certificate Information: 7701 S KITTYHAWK AVE 90045

Application / Permit
18014-30002-05396
Plan Check / Job No.
B20WL02845
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental ref to pcis # 18014-30000-05396, to change floor plans layout and extend addition to add a balcony at rear side and add roof at the entrance and update structural inventory
Permit Issued
Issued on 12/16/2020
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 12/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2020 APPLICANT
Assigned to Plan Check Engineer 7/29/2020 REZA HAGHIGHAT
Corrections Issued 8/3/2020 REZA HAGHIGHAT
Quality Review Completed 8/10/2020 TARIK SAOUD
Plan Check Approved 12/8/2020 REZA HAGHIGHAT
Issued 12/16/2020 APPLICANT
Building Plans Picked Up 12/17/2020 APPLICANT
Permit Finaled 12/1/2021 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development Cleared 11/12/2020 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 11/19/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 11/19/2020 DINAH GARIN
Green Code Cleared 12/8/2020 REZA HAGHIGHAT

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C38552 979 E MUNCIE AVE      FRESNO, CA 93720

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/12/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 1/12/2021 Partial Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 1/13/2021 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 11/23/2021 Conditional Approval BOBBY KEY
ELECTRICAL-Final 11/23/2021 Corrections Issued BOBBY KEY
Final 11/23/2021 Not Ready for Inspection BOBBY KEY
HVAC-Final 11/23/2021 Corrections Issued BOBBY KEY
PLUMBING-Final 11/23/2021 Approved BOBBY KEY
BUILDING-Rough-Frame 12/1/2021 Approved RICHARD STEINBACH
Final 12/1/2021 Permit Finaled RICHARD STEINBACH
Footing/Foundation/Slab 12/1/2021 Approved RICHARD STEINBACH