1251 E APPLETON WAY 90291
Certificate Information: 1251 E APPLETON WAY 90291
- Application / Permit
- 18014-30002-02612
- Plan Check / Job No.
- B19WL01807
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO PCIS 18014-30000-02612 TO ADD 2ND STORY ADDITION TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 9/9/2019
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 2/7/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2019 | LAMAR DAVIS |
| Corrections Issued | 4/22/2019 | LAMAR DAVIS |
| Green Plans Picked Up | 4/24/2019 | APPLICANT |
| Quality Review Completed | 5/2/2019 | FELIX FIGUEROA |
| Building Plans Picked Up | 5/6/2019 | APPLICANT |
| Applicant returned to address corrections | 7/15/2019 | LAMAR DAVIS |
| Plan Check Approved | 9/9/2019 | LAMAR DAVIS |
| Issued | 9/9/2019 | LADBS |
| Permit Finaled | 2/6/2020 | DAVID HEINE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/19/2019 | AL GAMBLE |
| ZA Case | Cleared | 7/10/2019 | NOAH MCCOY |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2019 | JEANIE LAM |
| Low Impact Development | Cleared | 7/15/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/15/2019 | JEANIE LAM |
| Sewer availability | Cleared | 7/15/2019 | JEANIE LAM |
| Green Code | Cleared | 7/17/2019 | RICHARD GARCIA |
| ZA Case | Cleared | 8/29/2019 | NOAH MCCOY |
| GPI Written Notices | Cleared | 9/9/2019 | AL GAMBLE |
Contact Information
| Architect | Carson, Thomas Darall; Lic. No.: C24160 | 1239 1/2 APPLETON WAY VENICE, CA 90291 |
| Contractor | Jeffery John Construction Inc; Lic. No.: 768268-B | 4863 LA MONTANA CIRCLE TARZANA, CA 91356 |
| Engineer | Germiyanoglu, Ismail; Lic. No.: S1505 | 144 N STANLEY DR BEVERLY HILLS, CA 90211 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2019 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 11/18/2019 | Partial Approval | DAVID HEINE |
| ELECTRICAL-Rough | 11/18/2019 | Approved | DAVID HEINE |
| Green Building Rough | 11/18/2019 | Approved | DAVID HEINE |
| HVAC-Rough | 11/18/2019 | Approved | DAVID HEINE |
| PLUMBING-Rough | 11/18/2019 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 11/26/2019 | Partial Approval | DAVID HEINE |
| Shower Pan | 12/3/2019 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 12/6/2019 | Approved | DAVID HEINE |
| Drywall Nailing | 12/11/2019 | Approved | DAVID FEILER |
| Final | 2/6/2020 | Permit Finaled | DAVID HEINE |
| Footing/Foundation/Slab | 2/6/2020 | Approved | DAVID HEINE |
| Green Building Final | 2/6/2020 | Approved | DAVID HEINE |
| Smoke Detectors | 2/6/2020 | Approved | DAVID HEINE |