8237 W ROXBURY ROAD 90069
Certificate Information: 8237 W ROXBURY ROAD 90069
- Application / Permit
- 18014-30001-06044
- Plan Check / Job No.
- B21WL04433
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental ref to pcis # 18014-30000-06044, due to change of design and addition.
- Permit Issued
- Issued on 4/27/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | ALFREDO JARA |
| Corrections Issued | 10/18/2021 | ALFREDO JARA |
| Quality Review Completed | 10/29/2021 | TARIK SAOUD |
| Building Plans Picked Up | 11/3/2021 | APPLICANT |
| Applicant returned to address corrections | 2/23/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 3/25/2022 | ALFREDO JARA |
| Plan Check Approved | 4/18/2022 | ALFREDO JARA |
| Issued | 4/27/2022 | APPLICANT |
| Permit Finaled | 10/27/2022 | RAUL BARAJAS |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/19/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/20/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2022 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 2/22/2022 | ALFREDO JARA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 1836 PARNELL AVE 202 LOS ANGELES, CA 90025 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/2/2022 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 5/2/2022 | Approved | RAUL BARAJAS |
| HVAC-Rough | 5/2/2022 | Approved | RAUL BARAJAS |
| Insulation | 5/4/2022 | Approved | RAUL BARAJAS |
| Drywall Nailing | 5/6/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 8/17/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 8/17/2022 | Approved | RAUL BARAJAS |
| Final | 8/17/2022 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/17/2022 | Approved | RAUL BARAJAS |
| HVAC-Final | 8/17/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 8/17/2022 | Approved | RAUL BARAJAS |
| Final | 10/27/2022 | Permit Finaled | RAUL BARAJAS |