17042 W BOLLINGER DR 90272
Certificate Information: 17042 W BOLLINGER DR 90272
- Application / Permit
- 18014-30001-04335
- Plan Check / Job No.
- B19WL00927
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTL TO PERMIT # 17014-30000-04335 TO CHANGE PROPOSED FLOOR PLAN IN REAR OF THE BUILDING RESULTING IN ADDITIONAL FLOOR AREA. (See Comments)
- Permit Issued
- Issued on 3/19/2019
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 2/21/2019 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 2/28/2019 | KAMRAN GHOTBI RAVANDI |
| Issued | 3/19/2019 | LADBS |
| Permit Finaled | 4/18/2022 | ANDREW NAVE |
Permit Application Clearance Information
| Coastal Zone | Cleared | 2/21/2019 | TREVOR MARTIN |
| Miscellaneous | Cleared | 2/21/2019 | TREVOR MARTIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2019 | ELAINE LEI |
| Low Impact Development | Cleared | 2/22/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/22/2019 | ELAINE LEI |
| Green Code | Cleared | 2/28/2019 | KAMRAN GHOTBI RAVANDI |
Contact Information
| Contractor | Mega Builders Inc; Lic. No.: 898347-B | 18375 VENTURA BLVD SUITE 520 TARZANA, CA 91356 |
| Engineer | Cai, Luo B; Lic. No.: C80352 | 5244 HUCKLEBERRY OAK STREET SIMI VALLEY, CA 93063 |
| Engineer | Song, Zhenyu Michael; Lic. No.: S5266 | 12540 DESTINO ST CERRITOS, CA 90703 |
| Engineer | Tsao, Tze-Tzong; Lic. No.: C46886 | 9428 ETON AVE STE M CHATSWORTH, CA 91311 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 4/8/2019 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 4/18/2022 | Approved | ANDREW NAVE |
| Drywall Nailing | 4/18/2022 | Approved | ANDREW NAVE |
| Final | 4/18/2022 | Permit Finaled | ANDREW NAVE |
| Footing/Foundation/Slab | 4/18/2022 | Approved | ANDREW NAVE |
| Green Building Final | 4/18/2022 | Approved | ANDREW NAVE |
| Green Building Rough | 4/18/2022 | Approved | ANDREW NAVE |
| Piling/Pier/Caisson | 4/18/2022 | Approved | ANDREW NAVE |
| Smoke Detectors | 4/18/2022 | Approved | ANDREW NAVE |