948 N LACHMAN LANE 90272

Certificate Information: 948 N LACHMAN LANE 90272

Application / Permit
18014-30001-02824
Plan Check / Job No.
B18WL06932
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO PERMIT 18014-30000-02824 TO REVISE INTERIOR LAYOUT, REVISE FOUNDATION AT (E) TRELLIS, ENCLOSE PORCH AT FRONT OF SFD. NO INCREASE IN FLOOR AREA
Permit Issued
Issued on 12/11/2018
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 6/1/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/30/2018 APPLICANT
Assigned to Plan Check Engineer 10/30/2018 LAMAR DAVIS
Corrections Issued 10/30/2018 LAMAR DAVIS
Issued 12/11/2018 LADBS
Permit Finaled 6/1/2023 GERMAN RODRIGUEZ MENDOZA

Permit Application Clearance Information

Miscellaneous Cleared 12/6/2018 TREVOR MARTIN
Coastal Zone Cleared 12/11/2018 TREVOR MARTIN
Miscellaneous Cleared 12/11/2018 TREVOR MARTIN

Contact Information

Architect Bini, Nicolo Giuseppe; Lic. No.: C29935 2114 COLDWATER CANYON DRIVE      BEVERLY HILLS, CA 90210
Contractor Owner-Builder       ,
Engineer Miyamoto, Yoshiaki Wayne; Lic. No.: L4825 4396 MENTONE AVE      CULVER CITY, CA 90230
Engineer Rhee, Kyle; Lic. No.: C78215 3855 W 7TH ST #304      LOS ANGELES, CA 90005

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/20/2018 Corrections Issued ANDREW NAVE
PLUMBING-Rough 12/20/2018 Partial Inspection ANDREW NAVE
Footing/Foundation/Slab 12/24/2018 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 1/3/2019 Corrections Issued ANDREW NAVE
Masonry Wall/Backfill 1/10/2019 Partial Inspection ANDREW NAVE
Masonry Wall/Backfill 1/29/2019 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 2/12/2019 Partial Inspection ANDREW NAVE
Excavation/Setback/Form/Re-Bar 2/27/2019 Approved ANDREW NAVE
Footing/Foundation/Slab 2/27/2019 Approved ANDREW NAVE
Footing/Foundation/Slab 4/25/2019 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 5/14/2019 Partial Inspection ANDREW NAVE
PLUMBING-Rough 5/14/2019 Partial Approval ANDREW NAVE
HVAC-Rough 11/21/2019 Approved ANDREW NAVE
ELECTRICAL-Rough 11/26/2019 Approved ANDREW NAVE
PLUMBING-Rough 11/27/2019 Partial Inspection DAVID FEILER
PLUMBING-Rough 12/9/2019 Partial Inspection ANDREW NAVE
Interior/Exterior Lathing 2/21/2020 Partial Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 2/26/2020 Approved ANDREW NAVE
Insulation 2/26/2020 Approved ANDREW NAVE
Drywall Nailing 3/13/2020 Partial Approval ANDREW NAVE
Shower Pan 4/3/2020 Corrections Issued ANDREW NAVE
Shower Pan 4/7/2020 Partial Approval ANDREW NAVE
Interior/Exterior Lathing 4/9/2020 Approved ANDREW NAVE
ELECTRICAL-Rough 4/28/2020 Approved ANDREW NAVE
PLUMBING-Rough 6/16/2020 Partial Inspection ANDREW NAVE