6332 W 5TH ST 90048
Certificate Information: 6332 W 5TH ST 90048
- Application / Permit
- 18014-30000-07131
- Plan Check / Job No.
- B18WL07855
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New ADU per AB 494 and SB 229
- Permit Issued
- Issued on 11/5/2019
- Issuing Office
- Metro
- Current Status
- Issued on 11/5/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2018 | RICARDO RAMIREZ |
| Corrections Issued | 12/24/2018 | RICARDO RAMIREZ |
| Building Plans Picked Up | 12/26/2018 | APPLICANT |
| Plan Check Approved | 10/16/2019 | RICARDO RAMIREZ |
| Issued | 11/5/2019 | LADBS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 8/23/2019 | JOHN CONNEALLY |
| Address approval | Cleared | 9/6/2019 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2019 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 9/6/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 9/6/2019 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 9/6/2019 | ANTHONY MAINEZ |
| Green Code | Cleared | 9/26/2019 | RICHARD GARCIA |
| Construction near power lines | Cleared | 10/16/2019 | RIDWAN HARDY |
Contact Information
| Architect | Gordon,, Brant Douglas; Lic. No.: C24403 | 12806 PACIFIC AVE 8 LOS ANGELES, CA 90066 |
| Contractor | G L Construction Group Inc; Lic. No.: 994049-B | 224 S DIAMOND BAR BLVD STE 367 DIAMOND BAR, CA 91765 |
| Engineer | Lin,, Jason K; Lic. No.: S6095 | 900 N SANTA ANITA AVE STE B ARCADIA, CA 91006 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/26/2019 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 12/30/2019 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 1/29/2020 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 1/29/2020 | Partial Approval | EVAN COOPER |
| Wood Frame | 2/27/2020 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 3/5/2020 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 3/5/2020 | Approved | EVAN COOPER |
| Green Building Rough | 3/5/2020 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 3/5/2020 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/5/2020 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 3/5/2020 | Approved | EVAN COOPER |
| Insulation | 3/20/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 3/20/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 3/31/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 5/28/2020 | Approved | EVAN COOPER |
| Final | 5/28/2020 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 5/28/2020 | Approved | EVAN COOPER |
| Green Building Final | 5/28/2020 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 5/28/2020 | Approved | EVAN COOPER |
| METHANE-Barrier | 5/28/2020 | Approved | EVAN COOPER |
| METHANE-Subgrade | 5/28/2020 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/28/2020 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 5/28/2020 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 5/28/2020 | Approved | EVAN COOPER |
| Final | 6/8/2020 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 6/8/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Service/Power Release | 6/8/2020 | Corrections Issued | CRAIG DAVIS |
| Final | 6/11/2020 | Conditional Approval | EVAN COOPER |
| Green Building Final | 6/11/2020 | Approved | EVAN COOPER |
| Service/Power Release | 6/11/2020 | Approved | EVAN COOPER |