- Permit Issued
- Issued on 10/8/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2018 | TARIK SAOUD |
| Corrections Issued | 12/17/2018 | TARIK SAOUD |
| Building Plans Picked Up | 12/26/2018 | APPLICANT |
| Plan Check Approved | 7/12/2019 | MANUEL GARCIA |
| Issued | 10/8/2019 | LADBS |
| CofO in Progress | 12/3/2021 | KEVIN SARGSYAN |
| Permit Finaled | 12/13/2021 | KENNETH NAGLE |
| CofO Issued | 12/13/2021 | KENNETH NAGLE |
| Permit Finaled | 12/13/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2019 | MAHELET GEBEYHU |
| CPC | Cleared | 6/12/2019 | NOAH MCCOY |
| CPC | Cleared | 6/12/2019 | NOAH MCCOY |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2019 | MAHELET GEBEYHU |
| Grading Pre-Inspection | Cleared | 6/12/2019 | TARIK SAOUD |
| Roof/Waste drainage to street | Cleared | 6/12/2019 | MAHELET GEBEYHU |
| Sewer availability | Cleared | 6/12/2019 | MAHELET GEBEYHU |
| Construction near power lines | Cleared | 7/9/2019 | WALTER RAMIREZ |
Contact Information
| Contractor | Jomar Construction Inc; Lic. No.: 824481-B | 1702 S ROBERTSON BL #182 LOS ANGELES, CA 90035 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/27/2020 | Corrections Issued | KEVIN SARGSYAN |
| Sewer | 8/27/2020 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 8/31/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Rough | 8/31/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/31/2020 | Partial Approval | KEVIN SARGSYAN |
| Pre-Inspection | 9/2/2020 | Partial Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/16/2020 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Barrier | 9/16/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 9/16/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/23/2020 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Barrier | 9/23/2020 | No Access for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 9/23/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/30/2020 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Barrier | 9/30/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 9/30/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 10/6/2020 | Approved | KEVIN SARGSYAN |
| METHANE-Barrier | 10/6/2020 | Approved | KEVIN SARGSYAN |
| METHANE-Subgrade | 10/6/2020 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/23/2020 | Partial Approval | KEVIN SARGSYAN |
| Masonry Wall/Backfill | 10/23/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/4/2020 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/4/2020 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 11/4/2020 | Approved | KEVIN SARGSYAN |
| Insulation | 11/4/2020 | Approved | KEVIN SARGSYAN |
| METHANE-Rough | 11/4/2020 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/4/2020 | Corrections Issued | KEVIN SARGSYAN |
| Wood Frame | 11/4/2020 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/10/2020 | Approved | KEVIN SARGSYAN |
| Gas Test | 11/10/2020 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 11/10/2020 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/10/2020 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 11/10/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Smoke Detectors | 11/10/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Drywall Nailing | 11/12/2020 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 11/17/2020 | Approved | KEVIN SARGSYAN |
| Shower Pan | 11/17/2020 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/13/2021 | Corrections Issued | KEVIN SARGSYAN |
| Final | 10/13/2021 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 10/13/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 10/13/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 10/13/2021 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/13/2021 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 10/13/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/19/2021 | Approved | KEVIN SARGSYAN |
| Final | 10/19/2021 | Conditional Approval | KEVIN SARGSYAN |
| Final | 12/3/2021 | OK to Issue CofO | KEVIN SARGSYAN |