10542 W CUSHDON AVE 90064

Certificate Information: 10542 W CUSHDON AVE 90064

Application / Permit
18014-30000-06964
Plan Check / Job No.
B18WL07703
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF EXISTING DETACHED 1-STORY TYPE VB 2-CAR GAGRAGE AND ADDITION TO CREATE ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 10/8/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2018 APPLICANT
Assigned to Plan Check Engineer 12/13/2018 TARIK SAOUD
Corrections Issued 12/17/2018 TARIK SAOUD
Building Plans Picked Up 12/26/2018 APPLICANT
Plan Check Approved 7/12/2019 MANUEL GARCIA
Issued 10/8/2019 LADBS
CofO in Progress 12/3/2021 KEVIN SARGSYAN
Permit Finaled 12/13/2021 KENNETH NAGLE
CofO Issued 12/13/2021 KENNETH NAGLE
Permit Finaled 12/13/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 6/12/2019 MAHELET GEBEYHU
CPC Cleared 6/12/2019 NOAH MCCOY
CPC Cleared 6/12/2019 NOAH MCCOY
Eng Process Fee Ord 176,300 Cleared 6/12/2019 MAHELET GEBEYHU
Grading Pre-Inspection Cleared 6/12/2019 TARIK SAOUD
Roof/Waste drainage to street Cleared 6/12/2019 MAHELET GEBEYHU
Sewer availability Cleared 6/12/2019 MAHELET GEBEYHU
Construction near power lines Cleared 7/9/2019 WALTER RAMIREZ

Contact Information

Contractor Jomar Construction Inc; Lic. No.: 824481-B 1702 S ROBERTSON BL #182      LOS ANGELES, CA 90035

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/27/2020 Corrections Issued KEVIN SARGSYAN
Sewer 8/27/2020 Approved KEVIN SARGSYAN
Green Building Rough 8/31/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Rough 8/31/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 8/31/2020 Partial Approval KEVIN SARGSYAN
Pre-Inspection 9/2/2020 Partial Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 9/16/2020 Partial Approval KEVIN SARGSYAN
METHANE-Barrier 9/16/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 9/16/2020 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 9/23/2020 Partial Approval KEVIN SARGSYAN
METHANE-Barrier 9/23/2020 No Access for Inspection KEVIN SARGSYAN
METHANE-Subgrade 9/23/2020 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 9/30/2020 Partial Approval KEVIN SARGSYAN
METHANE-Barrier 9/30/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 9/30/2020 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 10/6/2020 Approved KEVIN SARGSYAN
METHANE-Barrier 10/6/2020 Approved KEVIN SARGSYAN
METHANE-Subgrade 10/6/2020 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 10/23/2020 Partial Approval KEVIN SARGSYAN
Masonry Wall/Backfill 10/23/2020 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 11/4/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 11/4/2020 Corrections Issued KEVIN SARGSYAN
Green Building Rough 11/4/2020 Approved KEVIN SARGSYAN
Insulation 11/4/2020 Approved KEVIN SARGSYAN
METHANE-Rough 11/4/2020 Approved KEVIN SARGSYAN
PLUMBING-Rough 11/4/2020 Corrections Issued KEVIN SARGSYAN
Wood Frame 11/4/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 11/10/2020 Approved KEVIN SARGSYAN
Gas Test 11/10/2020 Partial Approval KEVIN SARGSYAN
HVAC-Rough 11/10/2020 Approved KEVIN SARGSYAN
PLUMBING-Rough 11/10/2020 Partial Approval KEVIN SARGSYAN
Shower Pan 11/10/2020 Not Ready for Inspection KEVIN SARGSYAN
Smoke Detectors 11/10/2020 Not Ready for Inspection KEVIN SARGSYAN
Drywall Nailing 11/12/2020 Approved KENNETH NAGLE
Interior/Exterior Lathing 11/17/2020 Approved KEVIN SARGSYAN
Shower Pan 11/17/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Final 10/13/2021 Corrections Issued KEVIN SARGSYAN
Final 10/13/2021 Corrections Issued KEVIN SARGSYAN
Green Building Final 10/13/2021 Approved KEVIN SARGSYAN
HVAC-Final 10/13/2021 Approved KEVIN SARGSYAN
PLUMBING-Final 10/13/2021 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/13/2021 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 10/13/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Final 10/19/2021 Approved KEVIN SARGSYAN
Final 10/19/2021 Conditional Approval KEVIN SARGSYAN
Final 12/3/2021 OK to Issue CofO KEVIN SARGSYAN