12315 W 15TH HELENA DR 90049
Certificate Information: 12315 W 15TH HELENA DR 90049
- Application / Permit
- 18014-30000-06854
- Plan Check / Job No.
- B18WL07603
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION & INTERIOR REMODEL OF (E) SINGLE FAMILY DWELLING W/ATT GARAGE
- Permit Issued
- Issued on 3/13/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2018 | APPLICANT |
| Green Plans Picked Up | 12/18/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2018 | LAMAR DAVIS |
| Corrections Issued | 12/26/2018 | LAMAR DAVIS |
| Quality Review Completed | 1/4/2019 | MARJAN SHENASI |
| Building Plans Picked Up | 1/4/2019 | APPLICANT |
| Applicant returned to address corrections | 1/25/2019 | LAMAR DAVIS |
| Plan Check Approved | 3/7/2019 | LAMAR DAVIS |
| Issued | 3/13/2019 | LADBS |
| CofO in Progress | 2/26/2021 | JOHN KIDWELL |
| CofO Issued | 3/15/2021 | VINCENT COTTON |
| Permit Finaled | 3/15/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/20/2018 | BRIAN OLSON |
| Certificate of Compliance | Cleared | 1/9/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 1/9/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 1/9/2019 | SARAH GOLDMAN |
| ZA Case | Cleared | 1/9/2019 | SARAH GOLDMAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2019 | JEANETTE VONG |
| Low Impact Development | Cleared | 1/17/2019 | JORGE MEJIA LEMUS |
| Green Code | Cleared | 3/6/2019 | RICHARD GARCIA |
| Miscellaneous | Cleared | 3/7/2019 | LAMAR DAVIS |
| Roof/Waste drainage to street | Cleared | 3/8/2019 | ADRIAN SANCHEZ |
Contact Information
| Architect | Norelius,, Bruce; Lic. No.: C32330 | BRUCE NORELIUS STUDIO 12450 ROCHEDALE LN. LOS ANGELES, CA 90049 |
| Contractor | Warner Technologies Inc; Lic. No.: 764311-B | 11693 SAN VICENTE BLVD #717 LOS ANGELES, CA 90049 |
| Engineer | Parker,, Leo Augustine; Lic. No.: S2829 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/18/2019 | Partial Approval | RICHARD STEINBACH |
| Sewer | 6/18/2019 | Partial Approval | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 6/26/2019 | Conditional Approval | TIM CHRISTENSEN |
| Sewer | 7/30/2019 | Partial Approval | DANNY TOLENTINO |
| PLUMBING-Rough | 8/8/2019 | Partial Approval | DANNY TOLENTINO |
| Wood Frame | 8/19/2019 | Partial Approval | TIM CHRISTENSEN |
| BUILDING-Rough-Frame | 8/27/2019 | Partial Approval | TIM CHRISTENSEN |
| Green Building Rough | 8/27/2019 | Not Ready for Inspection | TIM CHRISTENSEN |
| PLUMBING-Rough | 8/27/2019 | Partial Approval | TIM CHRISTENSEN |
| Underground Mechanical | 9/17/2019 | Partial Approval | DANNY TOLENTINO |
| BUILDING-Rough-Frame | 10/7/2019 | Conditional Approval | DANNY TOLENTINO |
| Green Building Rough | 10/7/2019 | Not Ready for Inspection | DANNY TOLENTINO |
| Insulation | 11/6/2019 | Partial Approval | TIM CHRISTENSEN |
| PLUMBING-Rough | 11/26/2019 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2019 | Conditional Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2020 | Partial Approval | DANNY TOLENTINO |
| Green Building Rough | 1/6/2020 | Not Ready for Inspection | DANNY TOLENTINO |
| Green Building Rough | 2/21/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| HVAC-Rough | 2/21/2020 | Corrections Issued | TIM CHRISTENSEN |
| PLUMBING-Rough | 2/21/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| BUILDING-Rough-Frame | 2/25/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| HVAC-Rough | 2/25/2020 | Partial Approval | TIM CHRISTENSEN |
| PLUMBING-Rough | 2/25/2020 | Partial Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 2/27/2020 | Conditional Approval | TIM CHRISTENSEN |
| PLUMBING-Rough | 2/27/2020 | Approved | TIM CHRISTENSEN |
| BUILDING-Rough-Frame | 3/16/2020 | Not Ready for Inspection | DANNY TOLENTINO |
| ELECTRICAL-Rough | 3/16/2020 | Corrections Issued | DANNY TOLENTINO |
| Green Building Rough | 3/16/2020 | Approved | DANNY TOLENTINO |
| HVAC-Rough | 3/16/2020 | Approved | DANNY TOLENTINO |
| BUILDING-Rough-Frame | 3/17/2020 | Approved | DANNY TOLENTINO |
| ELECTRICAL-Rough | 3/17/2020 | Approved | DANNY TOLENTINO |
| Insulation | 4/1/2020 | Approved | DANNY TOLENTINO |
| Drywall Nailing | 4/21/2020 | Approved | TIM CHRISTENSEN |
| Interior/Exterior Lathing | 6/2/2020 | Approved | TIM CHRISTENSEN |
| Shower Pan | 7/9/2020 | Corrections Issued | ROBERT SHELLY |
| Shower Pan | 7/10/2020 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 7/17/2020 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Final | 8/27/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 9/14/2020 | Approved | ANTHONY MCDOWALL |
| Final | 10/21/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 10/21/2020 | Approved | JOHN KIDWELL |
| Green Building Final | 10/21/2020 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 10/21/2020 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 10/21/2020 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 1/26/2021 | Approved | JOHN KIDWELL |
| HVAC-Final | 1/26/2021 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 1/26/2021 | Approved | JOHN KIDWELL |
| Final | 2/26/2021 | OK to Issue CofO | JOHN KIDWELL |