11818 W VICTORIA AVE 90066
Certificate Information: 11818 W VICTORIA AVE 90066
- Application / Permit
- 18014-30000-06852
- Plan Check / Job No.
- B18WL07600
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND FLOOR ADDITION TO EXISTING 1-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 10/7/2019
- Issuing Office
- Valley
- Current Status
- Issued on 10/7/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/3/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2019 | KAVIAN REFAHI |
| Corrections Issued | 1/7/2019 | KAVIAN REFAHI |
| Quality Review Completed | 1/14/2019 | MARJAN SHENASI |
| Building Plans Picked Up | 1/22/2019 | APPLICANT |
| Green Plans Picked Up | 1/22/2019 | APPLICANT |
| Applicant returned to address corrections | 7/31/2019 | KAVIAN REFAHI |
| Applicant returned to address corrections | 8/20/2019 | KAVIAN REFAHI |
| Applicant returned to address corrections | 9/18/2019 | KAVIAN REFAHI |
| Plan Check Approved | 9/25/2019 | KAVIAN REFAHI |
| Issued | 10/7/2019 | LADBS |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 1/7/2019 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 1/7/2019 | KAVIAN REFAHI |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 3/4/2019 | CHRISTINE REUSCH |
| Low Impact Development | Cleared | 7/15/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/18/2019 | OSCAR GUTIERREZ |
| Construction near power lines | Cleared | 9/20/2019 | RIDWAN HARDY |
| Green Code | Cleared | 9/25/2019 | RICHARD GARCIA |
Contact Information
| Contractor | Pacific Point Builders Inc; Lic. No.: 768984-B | 18340 VENTURA BLVD STE 210 TARZANA, CA 91356 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/6/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| Footing/Foundation/Slab | 12/6/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| Excavation/Setback/Form/Re-Bar | 12/16/2019 | Approved | KEVIN BEAULIEU |
| Footing/Foundation/Slab | 12/16/2019 | Conditional Approval | KEVIN BEAULIEU |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2020 | Not Ready for Inspection | KEVIN BEAULIEU |
| Footing/Foundation/Slab | 2/13/2020 | Approved | KEVIN BEAULIEU |
| PLUMBING-Rough | 2/13/2020 | Partial Approval | KEVIN BEAULIEU |
| BUILDING-Rough-Frame | 3/6/2020 | Partial Approval | KEVIN BEAULIEU |
| Green Building Rough | 3/6/2020 | Not Ready for Inspection | KEVIN BEAULIEU |
| ELECTRICAL-Rough | 7/30/2020 | No Access for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/30/2020 | No Access for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/31/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/31/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/4/2020 | Corrections Issued | KENNETH NAGLE |
| PLUMBING-Rough | 8/4/2020 | Not Ready for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 9/10/2020 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/19/2020 | Approved | EVAN COOPER |
| PLUMBING-Rough | 10/19/2020 | Approved | EVAN COOPER |
| HVAC-Rough | 11/24/2020 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 12/9/2020 | Not Ready for Inspection | RICHARD ROBLES |
| Green Building Rough | 12/9/2020 | Approved | RICHARD ROBLES |
| Special/Order Compliance | 12/9/2020 | Approved | RICHARD ROBLES |
| Deputy Wood Construction | 12/24/2020 | Conditional Approval | RICHARD ROBLES |
| Shower Pan | 1/15/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 1/22/2021 | Approved | EVAN COOPER |
| Insulation | 5/4/2021 | Corrections Issued | EVAN COOPER |
| Insulation | 5/7/2021 | Partial Approval | JESUS RODRIGUEZ |
| Special/Order Compliance | 5/7/2021 | Partial Inspection | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 5/10/2021 | Approved | KENNETH NAGLE |
| Insulation | 5/10/2021 | Approved | KENNETH NAGLE |
| Drywall Nailing | 5/18/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 11/23/2021 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 11/23/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 11/23/2021 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Final | 12/6/2021 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 12/6/2021 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Final | 12/6/2021 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 1/24/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 1/24/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 1/24/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 7/27/2022 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 7/27/2022 | Approved | JOHNNY MIRANDA |
| Final | 9/23/2025 | Corrections Issued | MICHAEL PELHAM |
| Final | 10/29/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 10/29/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 10/29/2025 | SGSOV Approved | RUBEN RIVAS |
| Smoke Detectors | 10/29/2025 | Approved | RUBEN RIVAS |