1942 N VAN NESS AVE 90068
Certificate Information: 1942 N VAN NESS AVE 90068
- Application / Permit
- 18014-30000-06831
- Plan Check / Job No.
- B18WL07576
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition ( conversion of existing attic to 2nd floor) and interior remodel
- Permit Issued
- Issued on 2/12/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2018 | KAVIAN REFAHI |
| Corrections Issued | 1/10/2019 | KAVIAN REFAHI |
| Quality Review Completed | 1/17/2019 | MARJAN SHENASI |
| Building Plans Picked Up | 1/22/2019 | APPLICANT |
| Green Plans Picked Up | 1/31/2019 | APPLICANT |
| Applicant returned to address corrections | 3/18/2019 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/2/2019 | KAVIAN REFAHI |
| Plan Check Approved | 11/12/2019 | KAVIAN REFAHI |
| Issued | 2/12/2020 | LADBS |
| CofO in Progress | 5/18/2021 | BRIAN SULLIVAN |
| CofO Issued | 8/14/2021 | DEROLD HAUFF |
| Permit Finaled | 8/14/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2019 | ZIXUAN CHEN |
| Roof/Waste drainage to street | Cleared | 2/4/2019 | ZIXUAN CHEN |
| Green Code | Cleared | 3/13/2019 | DONALD CRICHLOW |
| HPOZ | Cleared | 10/31/2019 | KATIE DEBIASE |
| Miscellaneous | Cleared | 10/31/2019 | KATIE DEBIASE |
| Grading Pre-Inspection | Cleared | 11/12/2019 | KAVIAN REFAHI |
Contact Information
| Contractor | Soltani Construction Inc; Lic. No.: 703647-B | 18341 SHERMAN WAY SUITE 104-B RESEDA, CA 91335 |
| Engineer | Sheikh,, Ijaz Ahmed; Lic. No.: S2392 | 5505 LAKEVIEW CANYON RD WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/27/2020 | Conditional Approval | ROBERT CORNELL |
| Footing/Foundation/Slab | 3/6/2020 | Conditional Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 4/7/2020 | Partial Approval | ROBERT CORNELL |
| ELECTRICAL-Rough | 4/7/2020 | Partial Approval | ROBERT CORNELL |
| Green Building Rough | 4/7/2020 | Not Ready for Inspection | ROBERT CORNELL |
| PLUMBING-Rough | 4/7/2020 | Partial Approval | ROBERT CORNELL |
| ELECTRICAL-Rough | 5/28/2020 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2020 | Conditional Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/28/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 6/11/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Wood Construction | 6/11/2020 | Conditional Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 6/12/2020 | Partial Approval | BRIAN SULLIVAN |
| HVAC-Rough | 6/12/2020 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 7/7/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/9/2020 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 7/9/2020 | Partial Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 7/9/2020 | Partial Approval | BRIAN SULLIVAN |
| Insulation | 7/15/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 7/21/2020 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/21/2020 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 7/21/2020 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 8/13/2020 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 8/13/2020 | Approved | BRIAN SULLIVAN |
| Insulation | 8/13/2020 | Partial Approval | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 8/13/2020 | Partial Approval | BRIAN SULLIVAN |
| Shower Pan | 8/13/2020 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/2/2020 | Partial Approval | BRIAN SULLIVAN |
| Drywall Nailing | 9/2/2020 | Partial Approval | BRIAN SULLIVAN |
| Insulation | 9/2/2020 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 9/2/2020 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/2/2020 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2020 | Partial Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 9/11/2020 | Approved | BRIAN SULLIVAN |
| Shower Pan | 9/11/2020 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 9/30/2020 | Approved | DONALD CRICHLOW |
| Gas Test | 9/30/2020 | Partial Approval | DONALD CRICHLOW |
| BUILDING-Rough-Frame | 1/26/2021 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 1/26/2021 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 1/26/2021 | Approved | BRIAN SULLIVAN |
| Final | 1/26/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 1/26/2021 | Approved | BRIAN SULLIVAN |
| Green Building Final | 1/26/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 1/26/2021 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 1/26/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 3/31/2021 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 3/31/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Smoke Detectors | 3/31/2021 | Approved | BRIAN SULLIVAN |
| Final | 5/18/2021 | OK to Issue CofO | BRIAN SULLIVAN |
| Green Building Final | 5/18/2021 | Approved | BRIAN SULLIVAN |