2619 N RUTHERFORD DR 90068

Certificate Information: 2619 N RUTHERFORD DR 90068

Application / Permit
18014-30000-06783
Plan Check / Job No.
B18WL07529
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO EXISTING 2-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 1/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/28/2018 APPLICANT
Assigned to Plan Check Engineer 12/20/2018 SERGIO SILVA
Corrections Issued 2/11/2019 SERGIO SILVA
Quality Review Completed 2/12/2019 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 2/12/2019 APPLICANT
Applicant returned to address corrections 5/28/2019 SERGIO SILVA
Plan Check Approved 6/26/2019 SERGIO SILVA
Issued 1/17/2020 LADBS
Building Plans Picked Up 1/24/2022 APPLICANT
CofO in Progress 8/15/2023 JOAQUIN GREENOUGH
Permit Finaled 8/15/2023 RONALD MYRICK
CofO Issued 8/15/2023 RONALD MYRICK
Permit Finaled 8/15/2023 RONALD MYRICK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/19/2019 JOSE CRUZ RODRIGUEZ
ZA Case Cleared 2/19/2019 SARAH GOLDMAN
Grading Pre-Inspection Cleared 5/29/2019 SERGIO SILVA
Roof/Waste drainage to street Cleared 5/29/2019 HISASHI KOBAYAKAWA
Permit Cleared 6/19/2019 KARAN PATEL
Green Code Cleared 6/25/2019 RICHARD GARCIA

Contact Information

Architect Bittoni,, Mark Christopher; Lic. No.: C34136 434 N GREENCRAIG ROAD      LOS ANGELES, CA 90049
Contractor Jbuilders Inc; Lic. No.: 1034385-B 6505 HESPERIA AVE      RESEDA, CA 91335
Engineer Yan,, Marcus; Lic. No.: C83553 24 GLENROSE AVE      DALY CITY, CA 94015

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/13/2020 Corrections Issued ROBERT CORNELL
Deputy Drilled-In Anchors 2/26/2020 Conditional Approval ROBERT CORNELL
Footing/Foundation/Slab 2/27/2020 Approved ROBERT CORNELL
Floor/Roof Diaphrgm/Shear Wall 3/18/2020 Partial Approval ROBERT CORNELL
Floor/Roof Diaphrgm/Shear Wall 3/20/2020 Approved ROBERT CORNELL
Insulation 3/20/2020 Approved ROBERT CORNELL
Floor/Roof Diaphrgm/Shear Wall 10/16/2020 Corrections Issued BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 10/22/2020 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 12/2/2020 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 12/2/2020 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 12/2/2020 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 12/2/2020 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 12/14/2020 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 12/14/2020 Partial Approval SCOTT FINNILA
Wood Frame 12/14/2020 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 12/22/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 12/22/2020 Approved FREDDIE RIVERA
Green Building Rough 12/22/2020 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 12/22/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 12/22/2020 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 1/28/2021 Corrections Issued BRIAN SULLIVAN
Green Building Rough 1/28/2021 Approved BRIAN SULLIVAN
Wood Frame 1/28/2021 Corrections Issued BRIAN SULLIVAN
Wood Frame 5/20/2021 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 6/9/2021 Not Ready for Inspection BRIAN SULLIVAN
Wood Frame 7/25/2022 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 9/28/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 9/28/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 9/28/2022 Approved JOAQUIN GREENOUGH
Insulation 10/6/2022 Approved JOAQUIN GREENOUGH
Drywall Nailing 11/2/2022 Corrections Issued JOAQUIN GREENOUGH
Interior/Exterior Lathing 11/2/2022 No Access for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/4/2022 Approved JOAQUIN GREENOUGH
Drywall Nailing 11/4/2022 Approved JOAQUIN GREENOUGH
Special/Order Compliance 11/12/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Interior/Exterior Lathing 11/14/2022 Partial Approval JOAQUIN GREENOUGH
Special/Order Compliance 11/14/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 11/29/2022 Approved RUBEN SALAS
Special/Order Compliance 3/15/2023 Corrections Issued STUART CHAPMAN
Special/Order Compliance 4/17/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Special/Order Compliance 4/18/2023 Partial Approval JOAQUIN GREENOUGH
Final 7/7/2023 Corrections Issued STUART CHAPMAN
Green Building Final 7/7/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 7/7/2023 SGSOV Approved STUART CHAPMAN
Smoke Detectors 7/7/2023 Approved STUART CHAPMAN
Final 7/24/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 7/28/2023 Conditional Approval STUART CHAPMAN
Final 8/2/2023 Partial Inspection JOAQUIN GREENOUGH
Final 8/3/2023 Corrections Issued JOAQUIN GREENOUGH
Final 8/9/2023 Corrections Issued JOAQUIN GREENOUGH
Final 8/15/2023 OK to Issue CofO JOAQUIN GREENOUGH