7305 N ENSIGN AVE 91352

Certificate Information: 7305 N ENSIGN AVE 91352

Application / Permit
18014-30000-06352
Plan Check / Job No.
B18WL07086
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT AND ADDITION TO ACCESSORY DWELLING UNIT. PER AB494 AND SB229.
Permit Issued
Issued on 1/31/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/3/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2018 APPLICANT
Assigned to Plan Check Engineer 11/15/2018 ALFREDO JARA
Corrections Issued 11/19/2018 ALFREDO JARA
Green Plans Picked Up 11/26/2018 APPLICANT
Quality Review Completed 11/30/2018 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 12/4/2018 APPLICANT
Plan Check Approved 1/24/2019 ALFREDO JARA
Issued 1/31/2019 LADBS
CofO in Progress 3/4/2020 RAYMOND KEHOE
CofO in Progress 3/4/2020 RAYMOND KEHOE
Permit Finaled 4/3/2020 MICHAEL SMITH
CofO Issued 4/3/2020 MICHAEL SMITH
Permit Finaled 4/3/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/3/2019 OSCAR GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 1/17/2019 ERIK BEASLEY
Low Impact Development Cleared 1/17/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/17/2019 ERIK BEASLEY
Sewer availability Cleared 1/17/2019 ERIK BEASLEY
Green Code Cleared 1/18/2019 ALFREDO JARA

Contact Information

Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/19/2019 No Access for Inspection MATTHEW NELSON
Underground Mechanical 3/19/2019 No Access for Inspection MATTHEW NELSON
Footing/Foundation/Slab 3/21/2019 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 3/28/2019 Partial Inspection THOMAS FINNILA
Underground Mechanical 3/28/2019 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 4/4/2019 Corrections Issued BEAU COLLINS
PLUMBING-Rough 4/8/2019 Approved DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 5/8/2019 Approved RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 8/19/2019 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 8/19/2019 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 8/22/2019 Partial Approval MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 8/22/2019 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/5/2019 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/5/2019 Partial Approval MISAEL ESPARZA
HVAC-Rough 9/5/2019 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 9/5/2019 Approved MISAEL ESPARZA
ELECTRICAL-Rough 9/12/2019 No Access for Inspection MISAEL ESPARZA
Shower Pan 9/12/2019 No Access for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 10/2/2019 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 10/2/2019 Approved MISAEL ESPARZA
Green Building Rough 10/2/2019 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 10/2/2019 Corrections Issued MISAEL ESPARZA
Shower Pan 10/2/2019 Corrections Issued MISAEL ESPARZA
HVAC-Rough 10/24/2019 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 10/24/2019 Corrections Issued MISAEL ESPARZA
Wood Frame 11/1/2019 Partial Approval KEVIN BEAULIEU
Wood Frame 11/5/2019 Approved MISAEL ESPARZA
Insulation 11/16/2019 Corrections Issued BEAU COLLINS
HVAC-Rough 12/20/2019 Approved MISAEL ESPARZA
Insulation 12/20/2019 Conditional Approval MISAEL ESPARZA
Interior/Exterior Lathing 12/20/2019 Partial Approval MISAEL ESPARZA
HVAC-Rough 12/24/2019 Approved DANIEL ORRANTE
Insulation 12/24/2019 Approved DANIEL ORRANTE
Drywall Nailing 1/2/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 1/2/2020 Approved MISAEL ESPARZA
Drywall Nailing 1/6/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 1/31/2020 Approved BEAU COLLINS
BUILDING-Rough-Frame 2/26/2020 Approved RAYMOND KEHOE
ELECTRICAL-Final 2/26/2020 Approved RAYMOND KEHOE
Final 2/26/2020 OK to Issue CofO RAYMOND KEHOE
Footing/Foundation/Slab 2/26/2020 Approved RAYMOND KEHOE
Green Building Final 2/26/2020 Approved RAYMOND KEHOE
HVAC-Final 2/26/2020 Approved RAYMOND KEHOE
PLUMBING-Final 2/26/2020 Approved RAYMOND KEHOE
SGSOV-Seismic Gas S/O Valve 2/26/2020 SGSOV Approved RAYMOND KEHOE
Smoke Detectors 2/26/2020 Approved RAYMOND KEHOE
Final 3/4/2020 OK to Issue CofO RAYMOND KEHOE