7305 N ENSIGN AVE 91352
Certificate Information: 7305 N ENSIGN AVE 91352
- Application / Permit
- 18014-30000-06352
- Plan Check / Job No.
- B18WL07086
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT AND ADDITION TO ACCESSORY DWELLING UNIT. PER AB494 AND SB229.
- Permit Issued
- Issued on 1/31/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2018 | ALFREDO JARA |
| Corrections Issued | 11/19/2018 | ALFREDO JARA |
| Green Plans Picked Up | 11/26/2018 | APPLICANT |
| Quality Review Completed | 11/30/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 12/4/2018 | APPLICANT |
| Plan Check Approved | 1/24/2019 | ALFREDO JARA |
| Issued | 1/31/2019 | LADBS |
| CofO in Progress | 3/4/2020 | RAYMOND KEHOE |
| CofO in Progress | 3/4/2020 | RAYMOND KEHOE |
| Permit Finaled | 4/3/2020 | MICHAEL SMITH |
| CofO Issued | 4/3/2020 | MICHAEL SMITH |
| Permit Finaled | 4/3/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2019 | OSCAR GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 1/17/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/17/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 1/17/2019 | ERIK BEASLEY |
| Green Code | Cleared | 1/18/2019 | ALFREDO JARA |
Contact Information
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/19/2019 | No Access for Inspection | MATTHEW NELSON |
| Underground Mechanical | 3/19/2019 | No Access for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/21/2019 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 3/28/2019 | Partial Inspection | THOMAS FINNILA |
| Underground Mechanical | 3/28/2019 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 4/4/2019 | Corrections Issued | BEAU COLLINS |
| PLUMBING-Rough | 4/8/2019 | Approved | DANIEL ORRANTE |
| Excavation/Setback/Form/Re-Bar | 5/8/2019 | Approved | RAYMOND KEHOE |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2019 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 8/19/2019 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2019 | Partial Approval | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 8/22/2019 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/5/2019 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2019 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 9/5/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 9/5/2019 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/12/2019 | No Access for Inspection | MISAEL ESPARZA |
| Shower Pan | 9/12/2019 | No Access for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/2/2019 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/2/2019 | Approved | MISAEL ESPARZA |
| Green Building Rough | 10/2/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 10/2/2019 | Corrections Issued | MISAEL ESPARZA |
| Shower Pan | 10/2/2019 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 10/24/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 10/24/2019 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 11/1/2019 | Partial Approval | KEVIN BEAULIEU |
| Wood Frame | 11/5/2019 | Approved | MISAEL ESPARZA |
| Insulation | 11/16/2019 | Corrections Issued | BEAU COLLINS |
| HVAC-Rough | 12/20/2019 | Approved | MISAEL ESPARZA |
| Insulation | 12/20/2019 | Conditional Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/20/2019 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 12/24/2019 | Approved | DANIEL ORRANTE |
| Insulation | 12/24/2019 | Approved | DANIEL ORRANTE |
| Drywall Nailing | 1/2/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 1/2/2020 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 1/6/2020 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/31/2020 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 2/26/2020 | Approved | RAYMOND KEHOE |
| ELECTRICAL-Final | 2/26/2020 | Approved | RAYMOND KEHOE |
| Final | 2/26/2020 | OK to Issue CofO | RAYMOND KEHOE |
| Footing/Foundation/Slab | 2/26/2020 | Approved | RAYMOND KEHOE |
| Green Building Final | 2/26/2020 | Approved | RAYMOND KEHOE |
| HVAC-Final | 2/26/2020 | Approved | RAYMOND KEHOE |
| PLUMBING-Final | 2/26/2020 | Approved | RAYMOND KEHOE |
| SGSOV-Seismic Gas S/O Valve | 2/26/2020 | SGSOV Approved | RAYMOND KEHOE |
| Smoke Detectors | 2/26/2020 | Approved | RAYMOND KEHOE |
| Final | 3/4/2020 | OK to Issue CofO | RAYMOND KEHOE |