10847 N NESTLE AVE 91326
Certificate Information: 10847 N NESTLE AVE 91326
- Application / Permit
- 18014-30000-06072
- Plan Check / Job No.
- B18WL06793
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL OF (E) 1-STORY SFD. RELOCATE KITCHEN AND ADD GUEST BEDROOM TO THE REAR OF THE DWELLING PER WFPP.
- Permit Issued
- Issued on 11/1/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/14/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2018 | JAHANSHAH POURHASSAN |
| Corrections Issued | 10/23/2018 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 11/1/2018 | ERWIN PASCUA |
| Issued | 11/1/2018 | LADBS |
| CofO in Progress | 12/9/2020 | JEFFREY PARD |
| CofO Issued | 12/14/2020 | JOHN JANSON |
| Permit Finaled | 12/14/2020 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2018 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 11/1/2018 | DENNIS BRAGIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/13/2018 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 12/14/2018 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2018 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 12/21/2018 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2019 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/4/2019 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/18/2019 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/18/2019 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 1/18/2019 | Approved | VINCENT HANLEY |
| Drywall Nailing | 2/1/2019 | Approved | VINCENT HANLEY |
| Insulation | 2/1/2019 | Approved | VINCENT HANLEY |
| Final | 12/3/2020 | Partial Approval | JEFFREY PARD |
| Green Building Final | 12/3/2020 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 12/3/2020 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 12/3/2020 | Approved | JEFFREY PARD |