2617 N SIERRA ST 90031
Certificate Information: 2617 N SIERRA ST 90031
- Application / Permit
- 18014-30000-05988
- Plan Check / Job No.
- B18WL06719
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) GARAGE TO ACCESSORY DWELLING UNIT. PER SB 494 AND SB 229. PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 7/12/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2018 | TARIK SAOUD |
| Corrections Issued | 10/29/2018 | TARIK SAOUD |
| Building Plans Picked Up | 10/30/2018 | APPLICANT |
| Plan Check Approved | 7/11/2019 | MANUEL GARCIA |
| Issued | 7/12/2019 | LADBS |
| CofO in Progress | 11/16/2022 | PATRICK LIEBREGT |
| Permit Finaled | 1/5/2023 | DANIEL SANCHEZ |
| CofO Issued | 1/5/2023 | DANIEL SANCHEZ |
| Permit Finaled | 1/5/2023 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 11/16/2018 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 11/16/2018 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 11/16/2018 | STEVE MELGAR |
| Permit | Cleared | 11/16/2018 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 12/5/2018 | ANGEL SALCEDO |
| CPC | Cleared | 12/11/2018 | TREVOR MARTIN |
| "D" conditions | Cleared | 3/14/2019 | SANTOS SANCHEZ |
| "Q" conditions | Cleared | 3/14/2019 | SANTOS SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2019 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 6/13/2019 | ELAINE LEI |
| Sewer availability | Cleared | 6/13/2019 | ELAINE LEI |
| Miscellaneous | Cleared | 7/10/2019 | DANIEL KOZUBAL |
| Grading Pre-Inspection | Cleared | 7/11/2019 | TARIK SAOUD |
Contact Information
| Contractor | Investors Design And Builders Inc; Lic. No.: 1003930-B | 4019 WEIK AVENUE BELL, CA 90201 |
Inspector Information
| THOMAS WILLIS, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JEFFREY CHRISTIAN, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| FERMIN RUBIO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JACOB SEGURA, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| CLAUDIO MORENO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK RUDE, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/15/2019 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 12/6/2019 | Approved | ARIS ALLAHVERDIAN |
| BUILDING-Rough-Frame | 1/8/2020 | Corrections Issued | PATRICK LIEBREGT |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2020 | Corrections Issued | PATRICK LIEBREGT |
| Green Building Rough | 1/8/2020 | Corrections Issued | PATRICK LIEBREGT |
| ELECTRICAL-Rough | 7/8/2020 | Not Ready for Inspection | PATRICK LIEBREGT |
| Interior/Exterior Lathing | 7/8/2020 | Not Ready for Inspection | PATRICK LIEBREGT |
| PLUMBING-Rough | 7/8/2020 | Not Ready for Inspection | PATRICK LIEBREGT |
| Wood Frame | 7/8/2020 | Not Ready for Inspection | PATRICK LIEBREGT |
| BUILDING-Rough-Frame | 11/9/2020 | Corrections Issued | PATRICK LIEBREGT |
| ELECTRICAL-Rough | 11/9/2020 | Not Ready for Inspection | PATRICK LIEBREGT |
| ELECTRICAL-Rough | 4/6/2022 | Approved | PATRICK LIEBREGT |
| Gas Test | 4/6/2022 | Approved | PATRICK LIEBREGT |
| Insulation | 4/6/2022 | Approved | PATRICK LIEBREGT |
| PLUMBING-Rough | 4/6/2022 | Approved | PATRICK LIEBREGT |
| Drywall Nailing | 4/14/2022 | Approved | PATRICK LIEBREGT |
| Service/Power Release | 4/14/2022 | Approved | PATRICK LIEBREGT |
| Shower Pan | 4/14/2022 | Approved | PATRICK LIEBREGT |
| BUILDING-Rough-Frame | 11/14/2022 | Approved | PATRICK LIEBREGT |
| Final | 11/14/2022 | Partial Inspection | PATRICK LIEBREGT |
| Footing/Foundation/Slab | 11/14/2022 | Approved | PATRICK LIEBREGT |
| Green Building Final | 11/14/2022 | Approved | PATRICK LIEBREGT |
| Green Building Rough | 11/14/2022 | Approved | PATRICK LIEBREGT |
| SGSOV-Seismic Gas S/O Valve | 11/14/2022 | SGSOV Approved | PATRICK LIEBREGT |
| Smoke Detectors | 11/14/2022 | Approved | PATRICK LIEBREGT |
| Final | 11/15/2022 | OK to Issue CofO | PATRICK LIEBREGT |