620 N SAN LORENZO ST 90402
Certificate Information: 620 N SAN LORENZO ST 90402
- Application / Permit
- 18014-30000-05877
- Plan Check / Job No.
- B18WL06609
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Renovation of (e) SFD and major remodel. Addition to connect exixting garage, recroom and servant's quarter to existing SFD and convert to be part of the SFD. Garage to remain. Connect existing laundry/bedroom building to SFD.
- Permit Issued
- Issued on 4/28/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2018 | APPLICANT |
| Green Plans Picked Up | 10/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2018 | MANUEL GARCIA |
| Corrections Issued | 11/5/2018 | MANUEL GARCIA |
| Quality Review Completed | 11/14/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/15/2019 | MANUEL GARCIA |
| Applicant returned to address corrections | 12/5/2019 | MANUEL GARCIA |
| Applicant returned to address corrections | 12/12/2019 | MANUEL GARCIA |
| Plan Check Approved | 12/19/2019 | MANUEL GARCIA |
| Issued | 4/28/2020 | LADBS |
| Building Plans Picked Up | 4/28/2020 | APPLICANT |
| CofO in Progress | 4/11/2025 | MEL KHACHATOURIAN |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
| CofO Issued | 4/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/29/2019 | JOSE CRUZ RODRIGUEZ |
| BHO/Hillside ordinance | Cleared | 3/29/2019 | JOSE CRUZ RODRIGUEZ |
| BHO/Hillside ordinance | Cleared | 3/29/2019 | JOSE CRUZ RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2019 | JOSE CRUZ RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 3/29/2019 | MANUEL GARCIA |
| Roof/Waste drainage to street | Cleared | 3/29/2019 | JOSE CRUZ RODRIGUEZ |
| ZA Case | Cleared | 4/4/2019 | ANNA VAN |
| Green Code | Cleared | 12/12/2019 | RICHARD GARCIA |
| Miscellaneous | Cleared | 12/16/2019 | JOE LUCKEY |
| Miscellaneous | Cleared | 12/16/2019 | JOE LUCKEY |
| ZA Case | Cleared | 12/16/2019 | JOE LUCKEY |
Contact Information
| Architect | Montalba,, David Desire; Lic. No.: C28726 | 2525 MICHIGAN AVENUE BLDG T4 SANTA MONICA, CA 90404 |
| Contractor | Owner-Builder | , |
| Engineer | Polon,, Gordon Leonard; Lic. No.: C28564 | 709 19TH STREET SANTA MONICA, CA 90402 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/15/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 10/7/2022 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 10/17/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/2/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 3/28/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/4/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 5/8/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Service/Power Release | 6/2/2023 | Approved | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 6/7/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 6/7/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 8/16/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/28/2023 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/29/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 1/29/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 1/29/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 1/29/2024 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 1/29/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 3/14/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/14/2024 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 3/14/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/14/2024 | Approved | ARAM AVEDISIAN |
| Insulation | 4/26/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/26/2024 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 5/14/2024 | Approved | ARAM AVEDISIAN |
| Shower Pan | 5/14/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/31/2024 | Partial Approval | KENNETH NAGLE |
| Gas Test | 10/7/2024 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 4/2/2025 | Approved | HERBERT GIRON |
| Green Building Final | 4/2/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 4/2/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 4/2/2025 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 4/2/2025 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 4/2/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 4/8/2025 | Corrections Issued | HERBERT GIRON |
| Final | 4/8/2025 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 4/8/2025 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 4/8/2025 | Not Ready for Inspection | HERBERT GIRON |
| Smoke Detectors | 4/8/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 4/10/2025 | Approved | MEL KHACHATOURIAN |
| HVAC-Final | 4/10/2025 | Approved | MEL KHACHATOURIAN |
| Final | 4/14/2025 | OK to Issue CofO | MEL KHACHATOURIAN |
| Green Building Final | 4/14/2025 | Approved | MEL KHACHATOURIAN |