12 N LATIMER ROAD 90402

Certificate Information: 12 N LATIMER ROAD 90402

Application / Permit
18014-30000-05296
Plan Check / Job No.
B18WL05972
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND ALTERATION TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
Permit Issued
Issued on 8/28/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2018 APPLICANT
Assigned to Plan Check Engineer 9/27/2018 KAMRAN GHOTBI RAVANDI
Corrections Issued 10/1/2018 KAMRAN GHOTBI RAVANDI
Quality Review Completed 10/3/2018 JASON HEALEY
Building Plans Picked Up 10/31/2018 APPLICANT
Applicant returned to address corrections 12/13/2018 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 12/17/2018 APPLICANT
Applicant returned to address corrections 1/16/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/18/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 8/14/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 8/28/2019 KAMRAN GHOTBI RAVANDI
Issued 8/28/2019 LADBS
CofO in Progress 2/6/2024 MICHAEL PELHAM
CofO in Progress 2/6/2024 MICHAEL PELHAM
Permit Finaled 2/7/2024 DANIEL ORRANTE
CofO Issued 2/7/2024 DANIEL ORRANTE
Permit Finaled 2/7/2024 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/30/2018 CHRISTOPHER LAW
BHO/Hillside ordinance Cleared 11/30/2018 CHRISTOPHER LAW
BHO/Hillside ordinance Cleared 11/30/2018 CHRISTOPHER LAW
Eng Process Fee Ord 176,300 Cleared 11/30/2018 CHRISTOPHER LAW
Miscellaneous Cleared 6/14/2019 NOAH MCCOY
Private street Cleared 6/14/2019 NOAH MCCOY
ZA Case Cleared 6/14/2019 NOAH MCCOY
Low Impact Development Cleared 7/16/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 7/16/2019 ELENA LOPEZ
Sewer availability Cleared 7/16/2019 ELENA LOPEZ
Excavation more than 5-ft deep Cleared 7/18/2019 CALOSHA APPROVED
Green Code Cleared 8/6/2019 RICHARD GARCIA

Contact Information

Contractor Naylor Construction; Lic. No.: 448826-B 20740 PACIFIC COAST HWY      MALIBU, CA 90265

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/18/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 10/17/2019 Partial Approval DANNY TOLENTINO
PLUMBING-Rough 10/17/2019 Not Ready for Inspection DANNY TOLENTINO
Footing/Foundation/Slab 11/7/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 1/6/2020 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 2/26/2020 Partial Approval DANNY TOLENTINO
Deputy Reinf. Concrete 2/28/2020 No Access for Inspection DANNY TOLENTINO
PLUMBING-Rough 3/25/2020 Partial Approval DANNY TOLENTINO
ELECTRICAL-Rough 4/23/2020 Not Ready for Inspection DANNY TOLENTINO
PLUMBING-Rough 4/23/2020 Partial Approval DANNY TOLENTINO
ELECTRICAL-Rough 4/24/2020 Partial Approval DANNY TOLENTINO
PLUMBING-Rough 4/24/2020 Not Ready for Inspection DANNY TOLENTINO
Footing/Foundation/Slab 5/7/2020 Partial Approval DANNY TOLENTINO
Deputy Reinf. Concrete 6/22/2020 Approved ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 7/16/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 7/16/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 8/17/2020 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 9/23/2020 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 11/25/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 12/8/2020 Partial Approval JOHN KIDWELL
PLUMBING-Rough 5/27/2021 No Access for Inspection JOHN KIDWELL
PLUMBING-Rough 6/2/2021 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 6/18/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 6/18/2021 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 6/18/2021 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 6/18/2021 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 6/18/2021 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 6/23/2021 Approved JOHN KIDWELL
ELECTRICAL-Rough 6/23/2021 Approved JOHN KIDWELL
Green Building Rough 6/23/2021 Approved JOHN KIDWELL
HVAC-Rough 6/23/2021 Approved JOHN KIDWELL
PLUMBING-Rough 6/23/2021 Approved JOHN KIDWELL
Insulation 7/19/2021 Approved PIERRE VEGA
Drywall Nailing 7/27/2021 Approved JOHNNY MIRANDA
Shower Pan 11/10/2021 Approved JOHN KIDWELL
Footing/Foundation/Slab 4/1/2022 Approved JOHN KIDWELL
Underground Mechanical 4/1/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 6/16/2022 Approved JOHN KIDWELL
Gas Test 1/23/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Final 6/8/2023 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 6/27/2023 Approved OGANES TARAKHCHYAN
Service/Power Release 7/10/2023 Approved KENNETH NAGLE
HVAC-Final 8/25/2023 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 8/25/2023 Approved CARLOS MATAMOROS
HVAC-Final 8/31/2023 Approved KENNETH NAGLE
PLUMBING-Final 8/31/2023 Approved KENNETH NAGLE
Final 12/21/2023 Corrections Issued ARAM AVEDISIAN
Green Building Final 12/21/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 12/21/2023 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 12/21/2023 Approved ARAM AVEDISIAN
Final 1/19/2024 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/19/2024 SGSOV Not Ready HERBERT GIRON
Final 1/26/2024 OK to Issue CofO MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 1/26/2024 SGSOV Approved MICHAEL PELHAM