13100 W WARREN AVE 90066

Certificate Information: 13100 W WARREN AVE 90066

Application / Permit
18014-30000-05096
Plan Check / Job No.
B18WL05768
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STROY ADDITION OF MASTER BEDROOM, BATHROOM AND CLOSET. CONVERT A BEDROOM AND BATHROOM TO 2 BEDROOMS AND 1 BATHROOM ON 2ND FLOOR. (N) ROOF DECK AND VEGITATED ROOF.
Permit Issued
Issued on 4/27/2020
Issuing Office
Current Status
CofO Issued on 6/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2018 APPLICANT
Assigned to Plan Check Engineer 10/4/2018 JAHANSHAH POURHASSAN
Green Plans Picked Up 10/15/2018 APPLICANT
Corrections Issued 10/30/2018 JAHANSHAH POURHASSAN
Quality Review Completed 11/7/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/5/2018 JAHANSHAH POURHASSAN
Plan Check Approved 12/12/2018 JAHANSHAH POURHASSAN
Issued 4/27/2020 APPLICANT
Building Plans Picked Up 5/19/2020 APPLICANT
CofO in Progress 5/18/2021 ENRIQUE MIRELES
Permit Finaled 6/4/2021 RONALD MYRICK
CofO Issued 6/4/2021 RONALD MYRICK
Permit Finaled 6/4/2021 RONALD MYRICK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/29/2018 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 11/29/2018 DENNIS BRAGIN
Sewer availability Cleared 11/29/2018 DENNIS BRAGIN
Grading Pre-Inspection Cleared 12/5/2018 JAHANSHAH POURHASSAN
Green Code Cleared 12/12/2018 RICHARD GARCIA

Contact Information

Architect Poloukhine,, Michael; Lic. No.: C32850 3489 MAPLEWOOD AVENUE      LOS ANGELES, CA 90066
Contractor Eberia Construction Inc; Lic. No.: 701330-B 8924 OLIN STREET      LOS ANGELES, CA 90034
Engineer Barajas,, Jorge Luis; Lic. No.: L8399 3635 SHADOW GROVE RD      PASADENA, CA 91107
Engineer Shirley,, Peter Franklin; Lic. No.: C75050 4429 DAWES AVE      CULVER CITY, CA 90230

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/10/2020 Approved ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 8/4/2020 Corrections Issued ANTHONY MCDOWALL
Wood Frame 9/3/2020 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 9/8/2020 Approved JOHNNY MIRANDA
Wood Frame 9/8/2020 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 10/9/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 10/9/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 10/22/2020 Partial Approval ENRIQUE MIRELES
Interior/Exterior Lathing 11/2/2020 Partial Approval JOHNNY MIRANDA
Shower Pan 11/2/2020 Corrections Issued JOHNNY MIRANDA
Interior/Exterior Lathing 11/5/2020 Partial Approval ENRIQUE MIRELES
Shower Pan 11/5/2020 Approved ENRIQUE MIRELES
Insulation 11/13/2020 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 11/13/2020 Partial Approval EVAN COOPER
Insulation 11/23/2020 Approved DAVID HEINE
Drywall Nailing 12/3/2020 Approved EVAN COOPER
PLUMBING-Final 4/6/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/16/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 4/16/2021 Approved ENRIQUE MIRELES
Final 4/16/2021 Corrections Issued ENRIQUE MIRELES
Green Building Final 4/16/2021 Approved ENRIQUE MIRELES
Green Building Rough 4/16/2021 Approved ENRIQUE MIRELES
HVAC-Final 4/16/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 4/16/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/16/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 4/16/2021 Approved ENRIQUE MIRELES
Final 4/29/2021 Partial Approval ENRIQUE MIRELES
HVAC-Final 5/3/2021 No Access for Inspection ENRIQUE MIRELES
Final 5/18/2021 OK to Issue CofO ENRIQUE MIRELES
Special/Order Compliance 6/3/2021 Approved ENRIQUE MIRELES