7716 N OSTROM AVE 91406

Certificate Information: 7716 N OSTROM AVE 91406

Application / Permit
18014-30000-04878
Plan Check / Job No.
B18WL05559
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND ADDITION TO REAR OF (E) SINGLE FAMILY DWELLING PER WOOD FRAME PRESCRIPTIVE PROVISIONS P/BC 2017-004.
Permit Issued
Issued on 12/19/2018
Issuing Office
Valley
Current Status
CofO Issued on 8/22/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2018 APPLICANT
Assigned to Plan Check Engineer 8/27/2018 LAMAR DAVIS
Corrections Issued 8/27/2018 LAMAR DAVIS
Applicant returned to address corrections 9/19/2018 TROY DEGUZMAN
Plan Check Approved 10/12/2018 MANUEL GARCIA
Issued 12/19/2018 LADBS
CofO in Progress 6/24/2020 DANIEL DREW
Permit Finaled 8/22/2020 MICHAEL SMITH
CofO Issued 8/22/2020 MICHAEL SMITH
Permit Finaled 8/22/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/27/2018 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 8/27/2018 DENNIS BRAGIN
Sewer availability Cleared 8/27/2018 DENNIS BRAGIN
Low Impact Development Cleared 10/12/2018 JORGE MEJIA LEMUS

Contact Information

Contractor Owner-Builder       ,
Engineer Dominguez, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/31/2018 Approved JOHN HAYES
Footing/Foundation/Slab 12/31/2018 Approved JOHN HAYES
BUILDING-Rough-Frame 1/14/2019 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 1/14/2019 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 1/14/2019 Corrections Issued JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 1/17/2019 Partial Inspection JACK KARGODORIAN
PLUMBING-Rough 1/17/2019 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 1/30/2019 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 1/30/2019 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 2/25/2019 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 3/12/2019 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 3/12/2019 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 3/12/2019 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 3/18/2019 Approved JACK KARGODORIAN
Wood Frame 3/18/2019 Approved JACK KARGODORIAN
Interior/Exterior Lathing 3/26/2019 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 4/4/2019 Partial Approval JACK KARGODORIAN
Wood Frame 4/4/2019 Approved JACK KARGODORIAN
Drywall Nailing 4/10/2019 Approved JACK KARGODORIAN
Green Building Rough 4/10/2019 Approved JACK KARGODORIAN
Interior/Exterior Lathing 4/16/2019 Approved JACK KARGODORIAN
Shower Pan 4/16/2019 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 2/5/2020 Approved JACK KARGODORIAN
Final 2/5/2020 Corrections Issued JACK KARGODORIAN
Green Building Final 2/5/2020 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 2/5/2020 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 2/5/2020 Not Ready for Inspection JACK KARGODORIAN
Final 2/27/2020 Corrections Issued JACK KARGODORIAN
Green Building Final 2/27/2020 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 2/27/2020 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 2/27/2020 Approved JACK KARGODORIAN
ELECTRICAL-Final 6/24/2020 Approved DANIEL DREW
Final 6/24/2020 OK to Issue CofO DANIEL DREW
Green Building Final 6/24/2020 Approved DANIEL DREW
HVAC-Final 6/24/2020 Approved DANIEL DREW
PLUMBING-Final 6/24/2020 Approved DANIEL DREW