4372-4374 S NEOSHO AVE 90066
Certificate Information: 4372-4374 S NEOSHO AVE 90066
- Application / Permit
- 18014-30000-04601
- Plan Check / Job No.
- B18WL05266
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) Detached Garage to Accessory Dwelling Unit. Per AB 494 and SB 229.
- Permit Issued
- Issued on 11/19/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2018 | ALFREDO JARA |
| Corrections Issued | 9/10/2018 | ALFREDO JARA |
| Green Plans Picked Up | 9/12/2018 | APPLICANT |
| Quality Review Completed | 9/20/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 9/20/2018 | APPLICANT |
| Plan Check Approved | 11/15/2018 | ALFREDO JARA |
| Issued | 11/19/2018 | LADBS |
| CofO in Progress | 9/24/2020 | JOHNNY MIRANDA |
| No Progress | 12/3/2020 | PIERRE VEGA |
| CofO in Progress | 12/3/2020 | PIERRE VEGA |
| CofO in Progress | 1/4/2021 | PIERRE VEGA |
| Permit Finaled | 1/5/2021 | VINCENT COTTON |
| CofO Issued | 1/5/2021 | VINCENT COTTON |
| Permit Finaled | 1/5/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 10/3/2018 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2018 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 10/3/2018 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 10/3/2018 | HISASHI KOBAYAKAWA |
| Green Code | Cleared | 11/15/2018 | RICHARD GARCIA |
Contact Information
| Architect | Tamm-Seitz, Aleksander; Lic. No.: C34163 | 1744 BROCKTON AVENUE # 105 LOS ANGELES, CA 90025 |
| Contractor | Intension Construction; Lic. No.: 956850-B | 1951 MALCOLM AVE #108 LOS ANGELES, CA 90023 |
| Engineer | Varela, Olivas Benjamin; Lic. No.: S5714 | 6080 CENTER DR STE 206 LOS ANGELES, CA 90045 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/10/2019 | Conditional Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 2/25/2019 | Approved | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2019 | Not Ready for Inspection | TIM CHRISTENSEN |
| PLUMBING-Rough | 5/2/2019 | Partial Approval | KENNETH NAGLE |
| ELECTRICAL-Rough | 5/16/2019 | Partial Approval | KENNETH NAGLE |
| PLUMBING-Rough | 5/16/2019 | Partial Approval | KENNETH NAGLE |
| BUILDING-Rough-Frame | 6/7/2019 | Partial Approval | KENNETH NAGLE |
| ELECTRICAL-Rough | 6/7/2019 | Approved | KENNETH NAGLE |
| Green Building Rough | 6/7/2019 | Approved | KENNETH NAGLE |
| HVAC-Rough | 6/7/2019 | Approved | KENNETH NAGLE |
| PLUMBING-Rough | 6/7/2019 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 12/16/2019 | Not Ready for Inspection | KENNETH NAGLE |
| Service/Power Release | 12/16/2019 | Not Required | KENNETH NAGLE |
| HVAC-Final | 12/17/2019 | Corrections Issued | KENNETH NAGLE |
| PLUMBING-Final | 12/17/2019 | Corrections Issued | KENNETH NAGLE |
| Service/Power Release | 1/22/2020 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 2/14/2020 | Corrections Issued | MICHAEL TEMPLE |
| HVAC-Final | 2/14/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| PLUMBING-Final | 2/14/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| ELECTRICAL-Final | 2/18/2020 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 2/18/2020 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Final | 2/18/2020 | Not Ready for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/21/2020 | Approved | CRAIG DAVIS |
| Drywall Nailing | 2/21/2020 | Approved | CRAIG DAVIS |
| Final | 2/21/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Final | 2/21/2020 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 2/21/2020 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 2/21/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 8/27/2020 | Not Ready for Inspection | KENNETH NAGLE |
| SGSOV-Seismic Gas S/O Valve | 8/27/2020 | SGSOV Approved | KENNETH NAGLE |
| Smoke Detectors | 8/27/2020 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 9/22/2020 | Approved | JOHNNY MIRANDA |
| Final | 9/22/2020 | Conditional Approval | JOHNNY MIRANDA |
| HVAC-Final | 9/22/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 9/22/2020 | Approved | JOHNNY MIRANDA |
| Final | 12/4/2020 | Corrections Issued | JOHNNY MIRANDA |