2618 N GREEN OAK PL 90068

Certificate Information: 2618 N GREEN OAK PL 90068

Application / Permit
18014-30000-04188
Plan Check / Job No.
B18WL04808
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Add Irregular shape (23'-6"x 59'-6") (N) 2nd floor and add (8'-10"x 14'-0") @ 1st floor, remodel to existing one story Single Family Dwelling with attached Garage."COMPLY WITH DEPARTMENT ORDER effective date 12/08/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 7/12/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2018 APPLICANT
Assigned to Plan Check Engineer 8/23/2018 TROY DEGUZMAN
Corrections Issued 8/27/2018 TROY DEGUZMAN
Quality Review Completed 9/7/2018 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 9/10/2018 APPLICANT
Green Plans Picked Up 9/10/2018 APPLICANT
Applicant returned to address corrections 10/31/2018 TROY DEGUZMAN
Applicant returned to address corrections 3/29/2019 TROY DEGUZMAN
Applicant returned to address corrections 4/11/2019 TROY DEGUZMAN
Applicant returned to address corrections 5/24/2019 TROY DEGUZMAN
Plan Check Approved 7/12/2019 TROY DEGUZMAN
Issued 7/12/2019 LADBS
CofO in Progress 10/8/2021 JOHN TCHANG
CofO Issued 10/20/2021 DANIEL SANCHEZ
Permit Finaled 10/20/2021 DANIEL SANCHEZ

Permit Application Clearance Information

GPI Written Notices Cleared 4/11/2019 TROY DEGUZMAN
Grading Pre-Inspection Cleared 4/11/2019 TROY DEGUZMAN
BHO/Hillside ordinance Cleared 4/26/2019 ELAINE LEI
BHO/Hillside ordinance Cleared 4/26/2019 ELAINE LEI
BHO/Hillside ordinance Cleared 4/26/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 4/26/2019 ELAINE LEI
Low Impact Development Cleared 4/26/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 4/26/2019 ELAINE LEI
Sewer availability Cleared 4/26/2019 ELAINE LEI
CPC Cleared 5/7/2019 ANNA VAN
Miscellaneous Cleared 5/8/2019 MICHAEL CASTILLO
Green Code Cleared 5/10/2019 DONALD CRICHLOW
"D" conditions Cleared 5/15/2019 RICHARD REASER
Hydrant and Access approval Cleared 5/24/2019 GEORGE SUCHAND

Contact Information

Architect Noteware, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Moran,, Cesar; Lic. No.: C72247 4500 E PACIFIC COAST HIGHWAY SUITE 210      LONG BEACH, CA 90804

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/2/2020 Partial Approval JOHN TCHANG
Footing/Foundation/Slab 3/17/2020 Partial Approval JOHN TCHANG
Footing/Foundation/Slab 3/25/2020 Partial Approval JOHN TCHANG
Footing/Foundation/Slab 5/1/2020 Corrections Issued GORDON ZUBER
Excavation/Setback/Form/Re-Bar 5/5/2020 Partial Approval JOHN TCHANG
Excavation/Setback/Form/Re-Bar 5/11/2020 Approved JOHN TCHANG
Footing/Foundation/Slab 5/11/2020 Approved JOHN TCHANG
Excavation/Setback/Form/Re-Bar 5/26/2020 Partial Approval EDDY ARDESSI
BUILDING-Rough-Frame 5/28/2020 Partial Approval JOHN TCHANG
Green Building Rough 5/28/2020 Not Ready for Inspection JOHN TCHANG
Floor/Roof Diaphrgm/Shear Wall 6/3/2020 Partial Approval JOHN TCHANG
BUILDING-Rough-Frame 6/22/2020 Corrections Issued JOHN TCHANG
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Not Ready for Inspection JOHN TCHANG
Green Building Rough 6/22/2020 Not Ready for Inspection JOHN TCHANG
Wood Frame 6/22/2020 Not Ready for Inspection JOHN TCHANG
BUILDING-Rough-Frame 7/13/2020 Not Ready for Inspection GORDON ZUBER
Floor/Roof Diaphrgm/Shear Wall 7/13/2020 Approved GORDON ZUBER
Green Building Rough 7/13/2020 Not Ready for Inspection GORDON ZUBER
BUILDING-Rough-Frame 8/31/2020 Corrections Issued JOHN TCHANG
Floor/Roof Diaphrgm/Shear Wall 8/31/2020 Not Ready for Inspection JOHN TCHANG
Green Building Rough 8/31/2020 Not Ready for Inspection JOHN TCHANG
Pool Piping 8/31/2020 Partial Inspection JOHN TCHANG
BUILDING-Rough-Frame 9/15/2020 Partial Approval JOHN TCHANG
Green Building Rough 9/15/2020 Approved JOHN TCHANG
Pre-Gunite 9/15/2020 Approved JOHN TCHANG
BUILDING-Rough-Frame 10/1/2020 Corrections Issued JOHN TCHANG
Wood Frame 10/1/2020 Partial Approval JOHN TCHANG
HVAC-Rough 10/22/2020 Corrections Issued JOHN TCHANG
BUILDING-Rough-Frame 11/4/2020 Partial Approval JOHN TCHANG
ELECTRICAL-Rough 11/4/2020 Approved JOHN TCHANG
Insulation 11/4/2020 Not Ready for Inspection JOHN TCHANG
Insulation 11/10/2020 Approved JOHN TCHANG
Drywall Nailing 12/1/2020 Approved JOHN TCHANG
HVAC-Rough 12/1/2020 Approved JOHN TCHANG
Shower Pan 12/1/2020 Approved JOHN TCHANG
Wood Frame 12/1/2020 Approved JOHN TCHANG
Interior/Exterior Lathing 12/9/2020 Approved JOHN TCHANG
BUILDING-Rough-Frame 9/8/2021 Approved JOHN TCHANG
Final 9/8/2021 Corrections Issued JOHN TCHANG
Green Building Final 9/8/2021 Approved JOHN TCHANG
SGSOV-Seismic Gas S/O Valve 9/8/2021 SGSOV Approved JOHN TCHANG
Smoke Detectors 9/8/2021 Approved JOHN TCHANG
Final 9/13/2021 Not Ready for Inspection JOHN TCHANG
Final 9/14/2021 Conditional Approval JOHN TCHANG
Gas Test 9/14/2021 Approved JOHN TCHANG