22020 W ALIZONDO DR 91364
Certificate Information: 22020 W ALIZONDO DR 91364
- Application / Permit
- 18014-30000-03768
- Plan Check / Job No.
- B18WL04372
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- complete remdel of the (E) house. adding 855 s.f vaulting ceilings, remove & replace windows & doors replumb entire sfr relocate and remodel kitchen and (E) master bdrm
- Permit Issued
- Issued on 7/29/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2018 | KAVIAN REFAHI |
| Plans on Hold | 8/15/2018 | JOSE RODRIGUEZ |
| Hold Released | 9/4/2018 | JOSE RODRIGUEZ |
| Corrections Issued | 9/12/2018 | KAVIAN REFAHI |
| Quality Review Completed | 9/20/2018 | TARIK SAOUD |
| Building Plans Picked Up | 9/25/2018 | APPLICANT |
| Applicant returned to address corrections | 12/20/2018 | KAVIAN REFAHI |
| Applicant returned to address corrections | 2/19/2019 | KAVIAN REFAHI |
| Applicant returned to address corrections | 5/9/2019 | KAVIAN REFAHI |
| Plan Check Approved | 5/21/2019 | KAVIAN REFAHI |
| Issued | 7/29/2019 | LADBS |
| CofO in Progress | 6/21/2023 | PETER FOLLING |
| Permit Finaled | 6/26/2023 | JOHN JANSON |
| CofO Issued | 6/26/2023 | JOHN JANSON |
| Permit Finaled | 6/26/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2018 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 7/27/2018 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 7/27/2018 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 7/27/2018 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2018 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 7/27/2018 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 9/13/2018 | LAMAR DAVIS |
| Miscellaneous | Cleared | 11/30/2018 | DOMINICK ORTIZ |
| Specific Plan | Cleared | 11/30/2018 | DOMINICK ORTIZ |
| GPI Written Notices | Cleared | 5/9/2019 | LAMAR DAVIS |
| Miscellaneous | Cleared | 5/9/2019 | LAMAR DAVIS |
| Low Impact Development | Cleared | 5/20/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 5/20/2019 | ELENA LOPEZ |
| Green Code | Cleared | 5/21/2019 | KAVIAN REFAHI |
Contact Information
| Contractor | Create R E Inc; Lic. No.: 999515-B | 909 NORTH SEPULVEDA #385 EL SEGUNDO, CA 90245 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/13/2019 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 11/13/2019 | Corrections Issued | JOHN JANSON |
| Excavation/Setback/Form/Re-Bar | 11/25/2019 | Not Ready for Inspection | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 12/9/2019 | Not Ready for Inspection | JOHN JANSON |
| Footing/Foundation/Slab | 12/9/2019 | Not Ready for Inspection | JOHN JANSON |
| Excavation/Setback/Form/Re-Bar | 12/13/2019 | Not Ready for Inspection | JOHN JANSON |
| Footing/Foundation/Slab | 12/24/2019 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 12/30/2019 | Approved | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 2/4/2020 | Partial Approval | STEVEN BACK |
| Reinforced Masonry Frame | 2/10/2020 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2020 | Partial Approval | PETER FOLLING |
| PLUMBING-Rough | 3/2/2020 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 3/5/2020 | Corrections Issued | PETER FOLLING |
| Underground Mechanical | 3/5/2020 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 3/10/2020 | Partial Approval | PETER FOLLING |
| BUILDING-Rough-Frame | 4/16/2020 | Partial Inspection | RONALD COWAN |
| Insulation | 4/16/2020 | Partial Approval | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2020 | Corrections Issued | MICHAEL TEMPLE |
| Wood Frame | 6/29/2020 | Partial Approval | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 10/22/2020 | Partial Inspection | PAUL CHOPP |
| PLUMBING-Rough | 10/22/2020 | Not Ready for Inspection | PAUL CHOPP |
| ELECTRICAL-Rough | 2/4/2021 | Partial Inspection | PAUL CHOPP |
| PLUMBING-Rough | 2/4/2021 | Corrections Issued | PAUL CHOPP |
| BUILDING-Rough-Frame | 4/8/2021 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 4/8/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 4/8/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 4/8/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 4/29/2021 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 4/29/2021 | Corrections Issued | DAVID SANDOVAL |
| Interior/Exterior Lathing | 4/29/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 4/29/2021 | Corrections Issued | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 6/7/2021 | Approved | PETER FOLLING |
| Green Building Rough | 6/7/2021 | Approved | PETER FOLLING |
| HVAC-Rough | 6/7/2021 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 6/7/2021 | Partial Approval | PETER FOLLING |
| Insulation | 7/9/2021 | Approved | PETER FOLLING |
| Drywall Nailing | 7/26/2021 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 7/29/2021 | Not Ready for Inspection | PETER FOLLING |
| Interior/Exterior Lathing | 10/12/2021 | Approved | MORRIS JACKSON |
| Shower Pan | 10/12/2021 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 5/9/2023 | Approved | PETER FOLLING |
| Final | 5/9/2023 | Corrections Issued | PETER FOLLING |
| Green Building Final | 5/9/2023 | Approved | PETER FOLLING |
| HVAC-Final | 5/9/2023 | Corrections Issued | PETER FOLLING |
| PLUMBING-Final | 5/9/2023 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV Not Ready | PETER FOLLING |
| Smoke Detectors | 5/9/2023 | Approved | PETER FOLLING |
| HVAC-Final | 6/5/2023 | No Access for Inspection | PETER FOLLING |
| Final | 6/7/2023 | Not Ready for Inspection | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 6/7/2023 | SGSOV Not Ready | PETER FOLLING |
| Final | 6/20/2023 | OK to Issue CofO | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 6/20/2023 | SGSOV Approved | PETER FOLLING |