1326 N GOUCHER ST 90272
Certificate Information: 1326 N GOUCHER ST 90272
- Application / Permit
- 18014-30000-02959
- Plan Check / Job No.
- B18WL03476
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 129 SF ADDITION, MAJOR INTERIOR REMODEL & CONVERT AN (E) 3RD FLOOR ROOF TO AN OPEN DECK TO AN (E) 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 11/7/2018
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 11/7/2018
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/30/2018 | APPLICANT |
| Green Plans Picked Up | 6/7/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2018 | ERWIN PASCUA |
| Corrections Issued | 7/1/2018 | ERWIN PASCUA |
| Quality Review Completed | 7/13/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 7/17/2018 | APPLICANT |
| Plan Check Approved | 8/28/2018 | ERWIN PASCUA |
| Issued | 11/7/2018 | LADBS |
Permit Application Clearance Information
| CPC | Cleared | 8/7/2018 | TREVOR MARTIN |
| CPC | Cleared | 8/7/2018 | TREVOR MARTIN |
| Roof/Waste drainage to street | Cleared | 8/17/2018 | KRISTEN LY |
| Green Code | Cleared | 8/23/2018 | DONALD CRICHLOW |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2018 | DENNIS BRAGIN |
| Grading Pre-Inspection | Cleared | 8/28/2018 | ERWIN PASCUA |
| Hydrant and Access approval | Cleared | 8/28/2018 | PEJMAN NOORI |
Contact Information
| Architect | , ; Lic. No.: C35150 | 2355 WESTWOOD BLVD # 834 LOS ANGELES, CA 90064 |
| Contractor | Classical Progression Inc; Lic. No.: 823135-B | 128 WADSWORTH AVE SANTA MONICA, CA 90405 |
| Engineer | , ; Lic. No.: C87550 | 1812 WESTHOLME AVE APT 11 LOS ANGELES, CA 90025 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/9/2019 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 9/18/2019 | Corrections Issued | DANNY TOLENTINO |
| PLUMBING-Rough | 9/20/2019 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 9/26/2019 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2019 | Corrections Issued | DANNY TOLENTINO |
| Footing/Foundation/Slab | 11/6/2019 | Corrections Issued | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2019 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 11/27/2019 | Partial Approval | DANNY TOLENTINO |
| Pre-Inspection | 4/14/2020 | Partial Inspection | DANNY TOLENTINO |
| Deputy Drilled-In Anchors | 6/26/2020 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/31/2020 | Partial Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 9/9/2020 | Approved | JOHN KIDWELL |
| Rough-Elec/Plmb/HVAC | 9/9/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 9/10/2020 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/10/2020 | Approved | JOHN KIDWELL |
| Grading Pre-Inspection | 9/22/2020 | Partial Inspection | MATTHEW JENKINS |
| Masonry Wall/Backfill | 10/13/2020 | Partial Approval | JOHN KIDWELL |
| Pre-Inspection | 12/16/2020 | Partial Inspection | MICHAEL PELHAM |
| Interior/Exterior Lathing | 1/15/2021 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 1/15/2021 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 1/22/2021 | Approved | JOHN KIDWELL |
| Green Building Rough | 1/22/2021 | Approved | JOHN KIDWELL |
| Insulation | 3/15/2021 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2021 | Conditional Approval | JOHN KIDWELL |
| Insulation | 4/6/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Wood Frame | 4/13/2021 | Partial Approval | JOHN KIDWELL |
| Shower Pan | 4/30/2021 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 5/26/2021 | Partial Approval | JOHN KIDWELL |
| Service/Power Release | 6/23/2022 | Approved | JOHN KIDWELL |
| Final | 7/20/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 7/20/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/20/2023 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 7/20/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 5/23/2024 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 5/23/2024 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 5/23/2024 | Not Ready for Inspection | ARAM AVEDISIAN |