13330 W SUNSET BLVD 90049

Certificate Information: 13330 W SUNSET BLVD 90049

Application / Permit
18014-30000-02423
Plan Check / Job No.
B18WL02840
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONSTRUCT (N) 719 S.F. SECOND STORY ADDITION TO (E) 1,770 S.F. ONE STORY SINGLE FAMILY DWELLING AND REMODEL (E) BATHROOMS AND BEDROOMS.
Permit Issued
Issued on 10/22/2018
Issuing Office
Metro
Current Status
CofO Issued on 8/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2018 APPLICANT
Assigned to Plan Check Engineer 5/24/2018 TROY DEGUZMAN
Corrections Issued 5/29/2018 TROY DEGUZMAN
Green Plans Picked Up 5/29/2018 APPLICANT
Quality Review Completed 6/8/2018 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 6/12/2018 APPLICANT
Plan Check Approved 7/10/2018 TROY DEGUZMAN
Issued 10/22/2018 LADBS
CofO in Progress 7/23/2024 ARAM AVEDISIAN
Permit Finaled 8/10/2024 DANIEL ORRANTE
CofO Issued 8/10/2024 DANIEL ORRANTE
Permit Finaled 8/10/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/29/2018 HISASHI KOBAYAKAWA
Sewer availability Cleared 5/29/2018 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 7/3/2018 GILBERT URREA
Low Impact Development Cleared 7/3/2018 MATTHEW JIMENEZ
Roof/Waste drainage to street Cleared 7/3/2018 STEVE MELGAR
Green Code Cleared 7/5/2018 RICHARD GARCIA
GPI Written Notices Cleared 7/10/2018 TROY DEGUZMAN
Grading Pre-Inspection Cleared 7/10/2018 TROY DEGUZMAN

Contact Information

Contractor Alex & Father Construction Inc; Lic. No.: 942352-B 3249 OVERLAND AVE #10      LOS ANGELES, CA 90034
Engineer Ilasin, John Lacebal; Lic. No.: C67469 1237 S VICTORIA AVENUE      OXNARD, CA 93035

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Elevation Certificate 11/21/2018 Approved MICHAEL PELHAM
Footing/Foundation/Slab 11/21/2018 Partial Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 1/22/2019 Corrections Issued KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 1/24/2019 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 6/5/2019 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 6/21/2019 Approved MICHAEL TEMPLE
ELECTRICAL-Rough 8/22/2019 Approved DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 8/22/2019 Partial Approval DANNY TOLENTINO
HVAC-Rough 8/22/2019 Corrections Issued DANNY TOLENTINO
PLUMBING-Rough 8/22/2019 Corrections Issued DANNY TOLENTINO
Wood Frame 8/22/2019 Corrections Issued DANNY TOLENTINO
Deputy Wood Construction 8/28/2019 Conditional Approval DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 9/4/2019 Partial Approval DANNY TOLENTINO
PLUMBING-Rough 9/4/2019 Approved DANNY TOLENTINO
Insulation 9/25/2019 Approved TIM CHRISTENSEN
Interior/Exterior Lathing 9/25/2019 Partial Approval TIM CHRISTENSEN
Shower Pan 9/25/2019 Approved TIM CHRISTENSEN
BUILDING-Rough-Frame 10/7/2019 Corrections Issued DANNY TOLENTINO
FLOOD-Proofing Certificate 10/7/2019 Approved DANNY TOLENTINO
Green Building Rough 10/7/2019 Approved DANNY TOLENTINO
PLUMBING-Rough 12/31/2020 Partial Inspection ANDREW NAVE
ELECTRICAL-Final 1/4/2021 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 7/13/2021 Approved JOHN KIDWELL
Drywall Nailing 7/13/2021 Approved JOHN KIDWELL
Final 7/13/2021 Corrections Issued JOHN KIDWELL
Green Building Final 7/13/2021 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 7/13/2021 SGSOV Approved JOHN KIDWELL
Smoke Detectors 7/13/2021 Approved JOHN KIDWELL
Final 7/22/2024 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 7/22/2024 Approved ARAM AVEDISIAN