3464 S GREENWOOD AVE 90066

Certificate Information: 3464 S GREENWOOD AVE 90066

Application / Permit
18014-30000-00960
Plan Check / Job No.
B18WL01173
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2 Story addition to existing one story single family dwelling with attached garage.
Permit Issued
Issued on 7/19/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2018 APPLICANT
Assigned to Plan Check Engineer 3/1/2018 RICARDO RAMIREZ
Corrections Issued 3/6/2018 RICARDO RAMIREZ
Quality Review Completed 3/16/2018 JOSE RODRIGUEZ
Building Plans Picked Up 3/30/2018 APPLICANT
Green Plans Picked Up 3/30/2018 APPLICANT
Applicant returned to address corrections 5/17/2018 RICARDO RAMIREZ
Plan Check Approved 7/19/2018 RICARDO RAMIREZ
Issued 7/19/2018 LADBS
CofO in Progress 6/22/2021 ENRIQUE MIRELES
CofO Issued 7/7/2021 VINCENT COTTON
Permit Finaled 7/7/2021 VINCENT COTTON

Permit Application Clearance Information

CPC Cleared 4/10/2018 EDBER MACEDO
CPC Cleared 4/10/2018 EDBER MACEDO
Eng Process Fee Ord 176,300 Cleared 4/10/2018 CELINA MORENO
Sewer availability Cleared 4/10/2018 CELINA MORENO
Grading Pre-Inspection Cleared 4/17/2018 AL GAMBLE
Low Impact Development Cleared 5/14/2018 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 5/14/2018 ADRIAN SANCHEZ
Green Code Cleared 5/17/2018 RICHARD GARCIA
Hold Cleared 1/23/2019 LOURDES RAMIRO

Contact Information

Engineer Parker, Leo Augustine; Lic. No.: S2829 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/28/2019 Approved THOMAS FINNILA
Footing/Foundation/Slab 3/13/2019 Partial Approval RICHARD STEINBACH
PLUMBING-Rough 5/23/2019 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 6/12/2019 No Access for Inspection KENNETH NAGLE
PLUMBING-Rough 6/14/2019 Partial Approval EVAN COOPER
Wood Frame 6/24/2019 Partial Approval EVAN COOPER
Insulation 6/28/2019 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/11/2019 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 8/14/2019 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/14/2019 Corrections Issued CRAIG DAVIS
Green Building Rough 8/14/2019 Not Ready for Inspection CRAIG DAVIS
Wood Frame 8/14/2019 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 9/12/2019 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 10/1/2019 Not Ready for Inspection JOHNNY MIRANDA
Green Building Rough 10/1/2019 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 10/11/2019 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/11/2019 Corrections Issued CRAIG DAVIS
Green Building Rough 10/11/2019 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 12/26/2019 Partial Approval CRAIG DAVIS
PLUMBING-Rough 4/9/2020 Approved DAVID FEILER
ELECTRICAL-Rough 4/30/2020 Approved DAVID FEILER
Sewer 4/30/2020 Approved DAVID FEILER
Interior/Exterior Lathing 5/1/2020 Partial Approval DAVID FEILER
HVAC-Rough 5/12/2020 Corrections Issued DAVID FEILER
HVAC-Rough 5/19/2020 Conditional Approval DAVID FEILER
BUILDING-Rough-Frame 5/21/2020 Conditional Approval DAVID FEILER
Green Building Rough 5/21/2020 Approved DAVID FEILER
HVAC-Rough 5/21/2020 Approved DAVID FEILER
BUILDING-Rough-Frame 5/26/2020 Approved DAVID FEILER
Insulation 5/26/2020 Approved DAVID FEILER
Drywall Nailing 6/26/2020 Not Ready for Inspection JOHNNY MIRANDA
Drywall Nailing 7/9/2020 Approved ANTHONY MCDOWALL
Shower Pan 8/10/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 8/24/2020 Partial Approval EVAN COOPER
Interior/Exterior Lathing 9/4/2020 Approved CRAIG DAVIS
Final 4/8/2021 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 4/8/2021 Approved ENRIQUE MIRELES
Green Building Final 4/8/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/8/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 4/8/2021 Approved ENRIQUE MIRELES
Structural Steel Frame 4/8/2021 Approved ENRIQUE MIRELES
Final 5/20/2021 Corrections Issued ENRIQUE MIRELES
Final 6/22/2021 OK to Issue CofO ENRIQUE MIRELES