4125 N BEVERLY GLEN BLVD 91423

Certificate Information: 4125 N BEVERLY GLEN BLVD 91423

Application / Permit
18014-30000-00682
Plan Check / Job No.
B18WL00840
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and remodel to the existing SFD with attached garage.
Permit Issued
Issued on 11/9/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2018 APPLICANT
Assigned to Plan Check Engineer 3/1/2018 JOSE RODRIGUEZ
Green Plans Picked Up 3/13/2018 APPLICANT
Corrections Issued 5/7/2018 JOSE RODRIGUEZ
Quality Review Completed 5/11/2018 JASON HEALEY
Building Plans Picked Up 5/17/2018 APPLICANT
Applicant returned to address corrections 8/9/2018 JOSE RODRIGUEZ
Applicant returned to address corrections 8/20/2018 JOSE RODRIGUEZ
Applicant returned to address corrections 8/27/2018 JOSE RODRIGUEZ
Applicant returned to address corrections 9/20/2018 JOSE RODRIGUEZ
Applicant returned to address corrections 9/27/2018 JOSE RODRIGUEZ
Plan Check Approved 10/9/2018 JOSE RODRIGUEZ
Issued 11/9/2018 LADBS
CofO in Progress 6/22/2022 JACK KARGODORIAN
CofO in Progress 6/23/2022 MATT KELLERMAN
CofO in Progress 6/24/2022 JACK KARGODORIAN
Permit Finaled 8/5/2022 DEROLD HAUFF
CofO Issued 8/5/2022 DEROLD HAUFF
Permit Finaled 8/5/2022 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/10/2018 JAMES MORALEZ
BHO/Hillside ordinance Cleared 8/10/2018 JAMES MORALEZ
BHO/Hillside ordinance Cleared 8/10/2018 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 8/10/2018 JAMES MORALEZ
Low Impact Development Cleared 8/10/2018 SAM NAVID
Roof/Waste drainage to street Cleared 8/10/2018 JAMES MORALEZ
Sewer availability Cleared 8/10/2018 JAMES MORALEZ
Grading Pre-Inspection Cleared 8/20/2018 JOSE RODRIGUEZ
Hydrant and Access approval Cleared 8/27/2018 PEJMAN NOORI
Green Code Cleared 8/29/2018 RICHARD GARCIA
Miscellaneous Cleared 8/29/2018 SARAH GOLDMAN
Miscellaneous Cleared 8/30/2018 JOHN LIN
Construction within easement Cleared 9/21/2018 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Miller, Karen Lynn; Lic. No.: GE2257 5364 DORIS WY      TORRANCE, CA 90505
Engineer Pirbadian, Amir; Lic. No.: C72413 5435 BALBOA BLVD 212      ENCINO, CA 91436
Geologist Van, Meter James L.; Lic. No.: EG2031 7702 CAPISTRANO AVE      WEST HILLS, CA 91304

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/25/2019 Conditional Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 10/2/2019 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 10/11/2019 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 10/17/2019 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/30/2019 No Access for Inspection JEFFREY PARD
Footing/Foundation/Slab 10/30/2019 No Access for Inspection JEFFREY PARD
Green Building Rough 10/30/2019 No Access for Inspection JEFFREY PARD
Verify Sprinkler Sign Off 10/30/2019 No Access for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 11/1/2019 Partial Approval DANIEL ORRANTE
Footing/Foundation/Slab 11/1/2019 Partial Approval DANIEL ORRANTE
Green Building Rough 11/1/2019 Not Ready for Inspection DANIEL ORRANTE
Verify Sprinkler Sign Off 11/1/2019 Not Ready for Inspection DANIEL ORRANTE
BUILDING-Rough-Frame 12/16/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 12/16/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 12/16/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/9/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 1/9/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 1/9/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/27/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 1/27/2020 Approved CHRISTOPHE COCHRAN
Green Building Rough 1/27/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 1/27/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 1/29/2020 Conditional Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 2/10/2020 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 2/10/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 2/10/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 2/10/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/11/2020 Corrections Issued CHRISTOPHE COCHRAN
Green Building Rough 3/11/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 3/11/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 3/11/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 3/12/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 3/12/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 3/17/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 3/17/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 3/18/2020 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 3/18/2020 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 3/23/2020 Partial Approval DANIEL ORRANTE
Underground Mechanical 3/23/2020 Approved DANIEL ORRANTE
BUILDING-Rough-Frame 3/25/2020 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 3/25/2020 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 3/25/2020 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 3/25/2020 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 4/2/2020 Not Ready for Inspection RONALD COWAN
Green Building Rough 4/2/2020 Not Ready for Inspection RONALD COWAN
HVAC-Rough 4/2/2020 Approved RONALD COWAN
Verify Sprinkler Sign Off 4/2/2020 Corrections Issued RONALD COWAN
BUILDING-Rough-Frame 4/17/2020 Not Ready for Inspection RAYMOND KEHOE
Green Building Rough 4/17/2020 Approved RAYMOND KEHOE
Interior/Exterior Lathing 4/17/2020 Partial Approval RAYMOND KEHOE
Shower Pan 4/17/2020 Approved RAYMOND KEHOE
Verify Sprinkler Sign Off 4/17/2020 Corrections Issued RAYMOND KEHOE
BUILDING-Rough-Frame 4/29/2020 Approved RAYMOND KEHOE
Special/Order Compliance 4/29/2020 Approved RAYMOND KEHOE
Verify Sprinkler Sign Off 4/29/2020 Approved RAYMOND KEHOE
Insulation 5/8/2020 Partial Approval GREGG CUMMINGS
Interior/Exterior Lathing 5/11/2020 Approved MICHEL ABAJAN
Drywall Nailing 6/2/2020 Approved THOMAS FINNILA
ELECTRICAL-Final 1/28/2021 Not Ready for Inspection CHARLES POWELL
Final 1/28/2021 Not Ready for Inspection CHARLES POWELL
Green Building Final 1/28/2021 Not Ready for Inspection CHARLES POWELL
HVAC-Final 1/28/2021 Not Ready for Inspection CHARLES POWELL
PLUMBING-Final 1/28/2021 Not Ready for Inspection CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 1/28/2021 SGSOV Not Ready CHARLES POWELL
Smoke Detectors 1/28/2021 Not Ready for Inspection CHARLES POWELL
Final 6/16/2021 Not Ready for Inspection CHARLES POWELL
Green Building Final 6/16/2021 Not Ready for Inspection CHARLES POWELL
Pre-Inspection 6/16/2021 Approved CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 6/16/2021 SGSOV Approved CHARLES POWELL
Final 4/4/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 4/4/2022 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 4/4/2022 Approved JACK KARGODORIAN
Final 4/8/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 4/8/2022 Approved JACK KARGODORIAN
ELECTRICAL-Final 5/24/2022 Approved JACK KARGODORIAN
Final 5/24/2022 Not Ready for Inspection JACK KARGODORIAN
Final 6/10/2022 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Final 6/22/2022 Approved JACK KARGODORIAN
Final 6/22/2022 Conditional Approval JACK KARGODORIAN
Final 6/24/2022 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 6/24/2022 Approved JACK KARGODORIAN