3705-3707 W EXPOSITION BLVD 90016

Certificate Information: 3705-3707 W EXPOSITION BLVD 90016

Application / Permit
18014-30000-00582
Plan Check / Job No.
B18WL00711
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
1ST AND 2ND FLOOR ADDITION AND CONVERSION OF 1-STORY TYPE VB SINGLE FAMILY DWELLING TO 2-STORY TYPE VB DUPLEX.
Permit Issued
Issued on 1/9/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2018 APPLICANT
Assigned to Plan Check Engineer 2/8/2018 SERGIO SILVA
Corrections Issued 2/13/2018 SERGIO SILVA
Quality Review Completed 2/23/2018 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 3/1/2018 APPLICANT
Applicant returned to address corrections 8/7/2018 SERGIO SILVA
Applicant returned to address corrections 8/28/2018 SERGIO SILVA
Applicant returned to address corrections 9/11/2018 SERGIO SILVA
Applicant returned to address corrections 9/14/2018 SERGIO SILVA
Green Plans Picked Up 9/14/2018 APPLICANT
Applicant returned to address corrections 12/11/2018 SERGIO SILVA
Plan Check Approved 1/9/2019 SERGIO SILVA
Issued 1/9/2019 LADBS
CofO in Progress 12/11/2021 STUART CHAPMAN
Permit Finaled 12/15/2021 DEROLD HAUFF
CofO Issued 12/15/2021 DEROLD HAUFF
Permit Finaled 12/15/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/6/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/18/2018 JAMES MORALEZ
Hydrant and Access approval Cleared 7/18/2018 GILBERT URREA
Sewer availability Cleared 7/18/2018 JAMES MORALEZ
Highway dedication Cleared 8/27/2018 STEVE MELGAR
Permit Cleared 9/6/2018 JAMES MORALEZ
Green Code Cleared 1/8/2019 DONALD CRICHLOW
Low Impact Development Cleared 1/8/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/8/2019 KARAN PATEL

Contact Information

Contractor Ivan Gabriel Vallejos; Lic. No.: 1024491-B 3707 EXPOSITION BLVD      LOS ANGELES, CA 90016
Engineer Cristescu, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/3/2019 Partial Approval CHARLENE BUSTAMANTE
Footing/Foundation/Slab 5/3/2019 Partial Approval CHARLENE BUSTAMANTE
METHANE-Barrier 5/3/2019 Approved CHARLENE BUSTAMANTE
METHANE-Subgrade 5/3/2019 Approved CHARLENE BUSTAMANTE
Deputy Drilled-In Anchors 5/16/2019 Conditional Approval CHARLENE BUSTAMANTE
Excavation/Setback/Form/Re-Bar 5/17/2019 Partial Inspection CHARLENE BUSTAMANTE
METHANE-Rough 5/17/2019 Approved CHARLENE BUSTAMANTE
Excavation/Setback/Form/Re-Bar 5/23/2019 Partial Approval CHARLENE BUSTAMANTE
Footing/Foundation/Slab 5/23/2019 Partial Approval CHARLENE BUSTAMANTE
Footing/Foundation/Slab 6/20/2019 Partial Approval PIERRE VEGA
Deputy Steel/Welding 6/21/2019 Conditional Approval CHARLENE BUSTAMANTE
Excavation/Setback/Form/Re-Bar 7/1/2019 Conditional Approval CHARLENE BUSTAMANTE
Pre-Inspection 7/1/2019 Approved CHARLENE BUSTAMANTE
Pre-Inspection 7/2/2019 Approved CHARLENE BUSTAMANTE
Floor/Roof Diaphrgm/Shear Wall 8/13/2019 Corrections Issued RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 8/16/2019 Partial Approval CHARLENE BUSTAMANTE
Floor/Roof Diaphrgm/Shear Wall 9/6/2019 Partial Approval CHARLENE BUSTAMANTE
Floor/Roof Diaphrgm/Shear Wall 11/19/2019 Partial Inspection JOSEPH MCGARRY
HVAC-Rough 11/19/2019 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 11/19/2019 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 11/21/2019 Approved CHARLENE BUSTAMANTE
HVAC-Rough 11/25/2019 Approved CHARLENE BUSTAMANTE
Interior/Exterior Lathing 12/26/2019 No Access for Inspection DANIEL GONZALEZ
Interior/Exterior Lathing 1/3/2020 Corrections Issued RAUL BARAJAS
Interior/Exterior Lathing 1/7/2020 Partial Approval CHARLENE BUSTAMANTE
Floor/Roof Diaphrgm/Shear Wall 1/14/2020 Conditional Approval RUBEN SALAS
Insulation 2/10/2020 Not Ready for Inspection ELMER BLAND
BUILDING-Rough-Frame 2/11/2020 Corrections Issued CHARLENE BUSTAMANTE
Green Building Rough 2/11/2020 Approved CHARLENE BUSTAMANTE
BUILDING-Rough-Frame 3/9/2020 Approved RICHARD STEINBACH
Drywall Nailing 3/9/2020 Approved RICHARD STEINBACH
Insulation 3/9/2020 Approved RICHARD STEINBACH
Interior/Exterior Lathing 3/9/2020 Approved RICHARD STEINBACH
Grading Pre-Inspection 7/7/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 9/11/2020 SGSOV Not Ready STUART CHAPMAN
Final 10/6/2020 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 10/6/2020 Approved STUART CHAPMAN
Green Building Final 10/6/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/6/2020 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 10/6/2020 Approved STUART CHAPMAN
Structural Steel Frame 10/6/2020 Approved STUART CHAPMAN
ELECTRICAL-Final 10/13/2020 Approved STUART CHAPMAN
Final 10/13/2020 Conditional Approval STUART CHAPMAN
HVAC-Final 10/13/2020 Approved STUART CHAPMAN
PLUMBING-Final 10/13/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/13/2020 SGSOV Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/14/2020 SGSOV Approved STUART CHAPMAN
Service/Power Release 10/14/2020 Approved STUART CHAPMAN
Final 3/22/2021 Conditional Approval STUART CHAPMAN
Final 12/11/2021 OK to Issue CofO STUART CHAPMAN