9939 N SALOMA AVE 91345

Certificate Information: 9939 N SALOMA AVE 91345

Application / Permit
18014-30000-00500
Plan Check / Job No.
B18WL00595
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to & conversion of (e) det. garage to an accessory dwelling unit (ADU) per AB 494 and SB 229.
Permit Issued
Issued on 12/2/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2018 APPLICANT
Assigned to Plan Check Engineer 2/13/2018 RICARDO RAMIREZ
Corrections Issued 2/13/2018 RICARDO RAMIREZ
Applicant returned to address corrections 1/17/2019 RICARDO RAMIREZ
Applicant returned to address corrections 11/22/2019 KAVIAN REFAHI
Plan Check Approved 12/2/2019 REZA HAGHIGHAT
Issued 12/2/2019 LADBS
CofO in Progress 8/2/2021 JENNIFER RABUCHIN
CofO Issued 10/26/2021 MICHAEL SMITH
Permit Finaled 10/26/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/22/2018 JOSEPH RHYU
Low Impact Development Cleared 1/10/2019 ANDRES COVARRUBIAS
Eng Process Fee Ord 176,300 Cleared 1/17/2019 MAHELET GEBEYHU
Roof/Waste drainage to street Cleared 1/17/2019 MAHELET GEBEYHU
Sewer availability Cleared 1/17/2019 MAHELET GEBEYHU
Construction near power lines Cleared 8/28/2019 RIDWAN HARDY

Contact Information

Architect Khoudikian,, Kaaren G; Lic. No.: C13183 6906 FOOTHILL BLVD.      TUJUNGA, CA 91042
Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/18/2019 Partial Inspection JENNIFER RABUCHIN
Pre-Inspection 2/26/2020 Partial Inspection JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 4/10/2020 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/28/2020 Partial Inspection BRENDAN LOONEY
Green Building Rough 5/28/2020 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 6/3/2020 Conditional Approval MISAEL ESPARZA
PLUMBING-Rough 6/3/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/4/2020 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 6/4/2020 Not Ready for Inspection GREGG CUMMINGS
Green Building Rough 6/4/2020 Corrections Issued GREGG CUMMINGS
Special/Order Compliance 6/4/2020 Approved PIERRE VEGA
BUILDING-Rough-Frame 6/8/2020 Approved GREGG CUMMINGS
ELECTRICAL-Rough 6/8/2020 Approved GREGG CUMMINGS
Green Building Rough 6/8/2020 Approved GREGG CUMMINGS
Special/Order Compliance 6/8/2020 Approved PIERRE VEGA
BUILDING-Rough-Frame 6/15/2020 Approved JENNIFER RABUCHIN
HVAC-Rough 6/16/2020 Corrections Issued JENNIFER RABUCHIN
Insulation 7/2/2020 Approved DANIEL ORRANTE
Drywall Nailing 7/9/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 1/6/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 4/7/2021 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 4/15/2021 Partial Approval JENNIFER RABUCHIN
Sewer 4/15/2021 Approved JENNIFER RABUCHIN
Underground Mechanical 4/15/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/9/2021 Approved JENNIFER RABUCHIN
Final 7/9/2021 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 7/9/2021 Approved JENNIFER RABUCHIN
Green Building Final 7/9/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 7/9/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 7/9/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/9/2021 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/9/2021 Corrections Issued JENNIFER RABUCHIN
Final 7/28/2021 OK to Issue CofO JENNIFER RABUCHIN
Gas Test 7/28/2021 Approved JENNIFER RABUCHIN
Green Building Final 7/28/2021 Approved JENNIFER RABUCHIN
HVAC-Final 7/28/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/28/2021 Approved JENNIFER RABUCHIN
Smoke Detectors 7/28/2021 Approved JENNIFER RABUCHIN
Special/Order Compliance 10/22/2021 Partial Inspection JENNIFER RABUCHIN