116 S BEACHWOOD DR 90004
Certificate Information: 116 S BEACHWOOD DR 90004
- Application / Permit
- 18014-30000-00222
- Plan Check / Job No.
- B18WL00247
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert detached garage/storage room to Accessory Dwelling Unit Per AB 494 & SB 229, addition and enclose existing stairs.
- Permit Issued
- Issued on 6/24/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2018 | HARLEN CARRAHER |
| Plan Check Approved | 3/27/2018 | MANUEL GARCIA |
| Plan Check Approved | 6/18/2018 | MANUEL GARCIA |
| Plan Check Approved | 9/11/2018 | MANUEL GARCIA |
| Issued | 6/24/2019 | LADBS |
| CofO in Progress | 2/14/2024 | RICHARD DOCKUS |
| CofO Issued | 3/20/2024 | DEROLD HAUFF |
| Permit Finaled | 3/20/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2018 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2018 | DENNIS BRAGIN |
| Sewer availability | Cleared | 1/25/2018 | DENNIS BRAGIN |
| HPOZ | Cleared | 2/1/2018 | KIMBERLY HENRY |
| Construction near power lines | Cleared | 3/23/2018 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/16/2019 | Corrections Issued | DANIEL GONZALEZ |
| Deputy Drilled-In Anchors | 9/29/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 12/8/2020 | Partial Inspection | JOSEPH MCGARRY |
| Green Building Rough | 12/8/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Rough | 12/8/2020 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 12/8/2020 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/20/2021 | No Access for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 1/20/2021 | No Access for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 1/20/2021 | No Access for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 1/20/2021 | No Access for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 1/20/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 1/25/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2021 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 1/25/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Sewer | 1/25/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/2/2021 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/2/2021 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 2/2/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 2/2/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 2/2/2021 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/2/2021 | Conditional Approval | JOSEPH MCGARRY |
| Shower Pan | 2/2/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 11/14/2022 | Not Ready for Inspection | JULIAN AMAYA |
| Final | 11/14/2022 | Corrections Issued | JULIAN AMAYA |
| Footing/Foundation/Slab | 11/14/2022 | Not Ready for Inspection | JULIAN AMAYA |
| Green Building Final | 11/14/2022 | Not Ready for Inspection | JULIAN AMAYA |
| METHANE-Barrier | 11/14/2022 | Not Ready for Inspection | JULIAN AMAYA |
| METHANE-Subgrade | 11/14/2022 | Not Ready for Inspection | JULIAN AMAYA |
| SGSOV-Seismic Gas S/O Valve | 11/14/2022 | SGSOV Not Ready | JULIAN AMAYA |
| Smoke Detectors | 11/14/2022 | Not Ready for Inspection | JULIAN AMAYA |
| BUILDING-Rough-Frame | 12/15/2023 | Approved | RICHARD DOCKUS |
| Final | 12/15/2023 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 12/15/2023 | Approved | RICHARD DOCKUS |
| Green Building Final | 12/15/2023 | Approved | RICHARD DOCKUS |
| METHANE-Barrier | 12/15/2023 | Approved | RICHARD DOCKUS |
| METHANE-Subgrade | 12/15/2023 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 12/15/2023 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 12/15/2023 | Approved | RICHARD DOCKUS |
| Final | 1/17/2024 | OK to Issue CofO | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Approved | RICHARD DOCKUS |
| Final | 3/12/2024 | Partial Inspection | JOAQUIN GREENOUGH |