4727 S LINDBLADE DR 90230
Certificate Information: 4727 S LINDBLADE DR 90230
- Application / Permit
- 18014-30000-00161
- Plan Check / Job No.
- B18WL00180
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) garage to accessory dwelling unit per AB2299 and SB1069
- Permit Issued
- Issued on 1/16/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2018 | KAVIAN REFAHI |
| Corrections Issued | 1/11/2018 | KAVIAN REFAHI |
| Plan Check Approved | 1/16/2018 | KAVIAN REFAHI |
| Issued | 1/16/2018 | LADBS |
| No Progress | 4/10/2026 | ANDREW NAVE |
| CofO in Progress | 4/10/2026 | ANDREW NAVE |
| Permit Finaled | 4/11/2026 | RICHARD STEINBACH |
| CofO Issued | 4/11/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/11/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2018 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2018 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 1/11/2018 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 1/12/2018 | HISASHI KOBAYAKAWA |
Contact Information
| Engineer | Mezey, Steven William; Lic. No.: S2665 | 14017 HARTSOOK ST SHERMAN OAKS, CA 91423 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/19/2018 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/19/2018 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/23/2018 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/24/2018 | Partial Approval | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 2/12/2018 | Conditional Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 3/6/2018 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 3/6/2018 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 3/6/2018 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 3/6/2018 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 3/20/2018 | Corrections Issued | CARLOS MATAMOROS |
| Shower Pan | 3/20/2018 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 7/11/2018 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/5/2018 | Partial Inspection | JONATHAN HOM |
| BUILDING-Rough-Frame | 9/14/2018 | Conditional Approval | JONATHAN HOM |
| BUILDING-Rough-Frame | 10/11/2018 | Approved | JONATHAN HOM |
| ELECTRICAL-Rough | 10/11/2018 | Approved | JONATHAN HOM |
| Insulation | 10/11/2018 | Partial Approval | JONATHAN HOM |
| PLUMBING-Rough | 10/11/2018 | Approved | JONATHAN HOM |
| ELECTRICAL-Final | 11/21/2018 | Not Ready for Inspection | JONATHAN HOM |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2018 | Not Ready for Inspection | JONATHAN HOM |
| Interior/Exterior Lathing | 11/29/2018 | Approved | JONATHAN HOM |
| Drywall Nailing | 2/12/2019 | Conditional Approval | JONATHAN HOM |
| HVAC-Final | 2/12/2019 | Corrections Issued | JONATHAN HOM |
| HVAC-Final | 7/19/2019 | Corrections Issued | JUAN VALENZUELA |
| Final | 12/30/2025 | Corrections Issued | DAVID FEILER |
| Drywall Nailing | 4/2/2026 | Approved | ANTHONY EGSON |
| Final | 4/2/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 4/2/2026 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 4/2/2026 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 4/8/2026 | Approved | ANTHONY EGSON |
| HVAC-Final | 4/8/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 4/8/2026 | Approved | ANTHONY EGSON |
| Final | 4/9/2026 | Conditional Approval | ANTHONY EGSON |