7338 N CANBY AVE 91335
Certificate Information: 7338 N CANBY AVE 91335
- Application / Permit
- 18014-20003-03407
- Plan Check / Job No.
- B21VN03387
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Day Care Facility adults
- Work Description
- - SUPPLEMENT TO 18014-20000-03407 TO ADD DOORS, WINDOWS AND SINKS. ADD STEEL MOMENT FRAME AT REAR OF BUILDING. PER ENGINEER DETAILS.
- Permit Issued
- Issued on 7/8/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | CHON CHIO KUO |
| Corrections Issued | 4/14/2021 | CHON CHIO KUO |
| Quality Review Completed | 4/19/2021 | STEVEN KIM |
| Applicant returned to address corrections | 5/24/2021 | CHON CHIO KUO |
| Plan Check Approved | 5/25/2021 | CHON CHIO KUO |
| Issued | 7/8/2021 | APPLICANT |
| Permit Finaled | 12/13/2022 | DANIEL VARNUM |
Permit Application Clearance Information
| DAS Clearance | Cleared | 5/6/2021 | CHON CHIO KUO |
Contact Information
| Contractor | J S Construction & Engineering Inc; Lic. No.: 1044634-B | 28924 TIMBERLANE ST AGOURA HILLS, CA 91301 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/13/2021 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 7/13/2021 | Conditional Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 7/16/2021 | Conditional Approval | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 7/30/2021 | Partial Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2021 | Not Ready for Inspection | CAMERON CHABAN |
| Deputy Wood Construction | 9/10/2021 | Conditional Approval | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2021 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 1/26/2022 | Corrections Issued | ANDREW DORSO |
| Final | 12/13/2022 | Permit Finaled | DANIEL VARNUM |
| Smoke Detectors | 12/13/2022 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 12/13/2022 | Approved | DANIEL VARNUM |
| Wood Frame | 12/13/2022 | Approved | DANIEL VARNUM |