10445 W BELLAGIO ROAD 90077

Certificate Information: 10445 W BELLAGIO ROAD 90077

Application / Permit
18014-20002-06253
Plan Check / Job No.
B19VN10861
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT TO 18014-20000-06253 TO LOWER EXISTING BASEMENT OF (E) SFD AND REVISE FRAMING AND FOUNDATION PLANS
Permit Issued
Issued on 8/22/2019
Issuing Office
Valley
Current Status
Permit Finaled on 12/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2019 APPLICANT
Assigned to Plan Check Engineer 7/1/2019 RAPHAEL ROSAS
Corrections Issued 7/1/2019 RAPHAEL ROSAS
Building Plans Picked Up 7/2/2019 APPLICANT
Plan Check Approved 8/22/2019 RAPHAEL ROSAS
Issued 8/22/2019 LADBS
Permit Finaled 12/28/2022 CHRISTOPHER WILSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/22/2019 RAPHAEL ROSAS

Contact Information

Contractor Benico Construction Inc; Lic. No.: 765501-B 245 SOUTH LA PEER DRIVE      BEVERLY HILLS, CA 90211
Engineer Naraghi-Arani,, Kamran; Lic. No.: C40985 30423 CANWOOD ST STE 223      AGOURA HILLS, CA 91301

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/20/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/8/2020 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 6/9/2020 Partial Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/10/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/10/2020 Partial Approval CHRISTOPHER WILSON
Wood Frame 6/10/2020 Partial Approval CHRISTOPHER WILSON
Final 12/28/2022 Permit Finaled CHRISTOPHER WILSON
Smoke Detectors 12/28/2022 Approved CHRISTOPHER WILSON
Special/Order Compliance 12/28/2022 Partial Inspection STEPHANIE SWANSON