648 E FLORENCE AVE 90001
Certificate Information: 648 E FLORENCE AVE 90001
- Application / Permit
- 18014-20002-05222
- Plan Check / Job No.
- B21VN01650
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- SUPPLEMENT TO 18014-10000-05222 FOR 29'0"X23'0" ADDITION TO (E) OFFICE BUILDING
- Permit Issued
- Issued on 2/7/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 8/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 2/26/2021 | APPLICANT |
| Green Plans Picked Up | 2/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | MARVEL DELACRUZ |
| Corrections Issued | 3/10/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 3/16/2021 | STEVEN KIM |
| Applicant returned to address corrections | 3/31/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 9/12/2022 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 9/16/2022 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 11/1/2022 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 12/7/2022 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 12/20/2022 | MARVEL DELACRUZ |
| Plan Check Approved | 12/21/2022 | MARVEL DELACRUZ |
| Issued | 2/7/2023 | APPLICANT |
| Permit Finaled | 7/23/2024 | DARRYL ARNOLD |
Permit Application Clearance Information
| Green Code | Cleared | 9/22/2021 | MICHAEL AYERS |
| Comm Cor/Mini-Mall | Cleared | 9/27/2021 | DANG NGUYEN |
| Comm Cor/Mini-Mall | Cleared | 9/27/2021 | DANG NGUYEN |
| Frnt yard landscape/Water mgmt | Cleared | 9/27/2021 | DANG NGUYEN |
| Specific Plan | Cleared | 9/27/2021 | DANG NGUYEN |
| ZI | Cleared | 9/27/2021 | DANG NGUYEN |
| Highway dedication | Cleared | 9/28/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2021 | RENZ SORIANO |
| Construction near power lines | Cleared | 2/12/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/12/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/22/2022 | JORGE MEJIA LEMUS |
| Trees in Parkway | Cleared | 4/20/2022 | ADALBERTO VERA |
| Permit | Cleared | 7/28/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 7/28/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 7/28/2022 | JEANETTE VONG |
| DAS Clearance | Cleared | 8/23/2022 | MARVEL DELACRUZ |
| Community Plan Implem. Overlay | Cleared | 12/14/2022 | HELEN JADALI |
| ZI | Cleared | 12/14/2022 | HELEN JADALI |
| ZI | Cleared | 12/21/2022 | DAVID URITA |
Contact Information
| Architect | Herrera,, Victor Javier; Lic. No.: C37003 | 9631 S. 4TH AVENUE INGLEWOOD, CA 90305 |
| Contractor | G W Construction; Lic. No.: 833648-B | 2937 VIRGINA AVE SANTA MONICA, CA 90404 |
| Engineer | Hoballah,, Tarek Ali; Lic. No.: S4124 | 2600 E PACIFIC COAST HWY STE 170 LONG BEACH, CA 90804 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/17/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 3/8/2023 | Approved | JULIAN CAPUCETTI |
| Deputy Reinf. Concrete | 3/10/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Approved | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Partial Approval | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 6/21/2023 | Approved | JULIAN CAPUCETTI |
| Green Building Rough | 8/1/2023 | Approved | MARTIN TAVITIAN |
| Wood Frame | 8/1/2023 | Conditional Approval | MARTIN TAVITIAN |
| Pre-Inspection | 10/30/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Pre-Inspection | 11/1/2023 | Corrections Issued | DARRYL ARNOLD |
| Grading Pre-Inspection | 11/8/2023 | Approved | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 12/8/2023 | Partial Approval | LUIS CCAMACHO |
| Excavation/Setback/Form/Re-Bar | 12/12/2023 | Approved | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 12/28/2023 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 5/21/2024 | Approved | ALFREDO LOPEZ |
| Final | 5/21/2024 | Partial Approval | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 5/21/2024 | Approved | ALFREDO LOPEZ |
| Green Building Final | 5/21/2024 | Approved | ALFREDO LOPEZ |
| Smoke Detectors | 5/21/2024 | Approved | ALFREDO LOPEZ |
| Wood Frame | 5/21/2024 | Approved | ALFREDO LOPEZ |
| Final | 7/23/2024 | Permit Finaled | DARRYL ARNOLD |