14146 W WEIDNER ST 91331

Certificate Information: 14146 W WEIDNER ST 91331

Application / Permit
18014-20002-00253
Plan Check / Job No.
B19VN01532
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL TO PERMIT# 18014-20000-00253 TO REVISE SCOPE OF WORK TO BE NEW DETACHED 30' 11" X 18' 1-STORY ACCESSORY DWELLING UNIT. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 10/21/2019
Issuing Office
Valley
Current Status
Permit Finaled on 1/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2019 APPLICANT
Assigned to Plan Check Engineer 2/7/2019 GURUNATH NESARAJAH
Corrections Issued 2/9/2019 GURUNATH NESARAJAH
Quality Review Completed 2/12/2019 OMID HEDAYAT
Building Plans Picked Up 2/20/2019 APPLICANT
Plan Check Approved 9/23/2019 GURUNATH NESARAJAH
Issued 10/21/2019 LADBS
Permit Finaled 1/5/2023 JENNIFER RABUCHIN

Permit Application Clearance Information

Construction near power lines Cleared 8/19/2019 RIDWAN HARDY
Address approval Cleared 8/26/2019 JOSHUA DIAZ
Eng Process Fee Ord 176,300 Cleared 8/26/2019 JOSHUA DIAZ
Hydrant and Access approval Cleared 8/26/2019 GILBERT URREA
Roof/Waste drainage to street Cleared 8/26/2019 JOSHUA DIAZ
Sewer availability Cleared 8/26/2019 JOSHUA DIAZ
Low Impact Development Cleared 9/17/2019 ANDRES COVARRUBIAS

Contact Information

Contractor Owner-Builder       ,
Engineer Sayah,, Daniel Hoshyar; Lic. No.: S6000 15233 VENTURA BLVD 1130      SHERMAN OAKS, CA 91403

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 10/28/2019 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 12/27/2019 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 10/22/2020 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/6/2020 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 11/23/2020 Corrections Issued JENNIFER RABUCHIN
Wood Frame 7/9/2021 Approved JENNIFER RABUCHIN
Insulation 8/4/2021 Approved WILLIAM WREN
Drywall Nailing 8/10/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/15/2021 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 10/5/2021 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 10/15/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/5/2023 Approved JENNIFER RABUCHIN
Final 1/5/2023 Permit Finaled JENNIFER RABUCHIN
MERV13>=Final 1/5/2023 Approved JENNIFER RABUCHIN
MERV13>=Rough 1/5/2023 Approved JENNIFER RABUCHIN
METHANE-Final 1/5/2023 Approved JENNIFER RABUCHIN
METHANE-Rough 1/5/2023 Approved JENNIFER RABUCHIN
Smoke Detectors 1/5/2023 Approved JENNIFER RABUCHIN