2119 W LAS COLINAS AVE 90041
Certificate Information: 2119 W LAS COLINAS AVE 90041
- Application / Permit
- 18014-20001-05726
- Plan Check / Job No.
- B22VN03026
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental to 18014-20000-05726 to revise the dimension of addition to 14'-6" x 38'-8" & revise site and floor plan.
- Permit Issued
- Issued on 3/29/2022
- Issuing Office
- Current Status
- Permit Finaled on 3/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2022 | OMID HEDAYAT |
| Corrections Issued | 3/24/2022 | OMID HEDAYAT |
| Plan Check Approved | 3/29/2022 | OMID HEDAYAT |
| Issued | 3/29/2022 | APPLICANT |
| Permit Finaled | 3/10/2023 | CRAIG VAUGHAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 3/23/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/25/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Badilla, Garces, Maria Elena; Lic. No.: C81817 | 3505 S WHITINGHAM DR WEST COVINA, CA 91792 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/31/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/31/2022 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/3/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/21/2022 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 6/21/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Sewer | 6/21/2022 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/7/2022 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 7/7/2022 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 7/7/2022 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 7/7/2022 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 7/19/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 7/19/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Insulation | 8/25/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 9/2/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/9/2022 | Partial Approval | SCOTT FINNILA |
| Shower Pan | 9/13/2022 | Corrections Issued | BRIAN SULLIVAN |
| Drywall Nailing | 9/16/2022 | No Access for Inspection | JEFFREY MEAD |
| Interior/Exterior Lathing | 9/21/2022 | Partial Approval | SCOTT FINNILA |
| Shower Pan | 9/21/2022 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 11/7/2022 | Approved | CRAIG VAUGHAN |
| Final | 11/7/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 11/7/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 11/7/2022 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 11/7/2022 | Corrections Issued | CRAIG VAUGHAN |