5457 N BECKFORD AVE 91356

Certificate Information: 5457 N BECKFORD AVE 91356

Application / Permit
18014-20001-05706
Plan Check / Job No.
B21VN09957
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO 18014-20000-05706 TO ADD NEW 24'9" X 7'6" AT FRONT OF SFD TO ENLARGE THE LIVING ROOM , ADD NEW (1) BATHROOM , REMODEL (2) BEDROOMS , (2) BATHROOMS, RELOCATE LAUNDRY ROOM, REPLACE EXISTING WINDOWS , RE-FRAME ROOF, TO CORRECT ADDITION AREA FOR MAIN PERMIT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/2/2021
Issuing Office
Current Status
Permit Finaled on 2/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2021 APPLICANT
Assigned to Plan Check Engineer 7/28/2021 RARES BODEA
Corrections Issued 8/2/2021 RARES BODEA
Plan Check Approved 9/2/2021 RARES BODEA
Issued 9/2/2021 APPLICANT
Permit Finaled 2/1/2022 DAVID SANDOVAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/4/2021 DAGOVERTO GUERRERO
Low Impact Development Cleared 8/19/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/20/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 9/2/2021 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Shaolian,, Shahab Joseph; Lic. No.: C84155 5104 GARDEN GROVE      TARZANA, CA 91356

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/9/2021 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 9/9/2021 Approved VINCENT HANLEY
Footing/Foundation/Slab 9/9/2021 Approved VINCENT HANLEY
Pre-Inspection 9/9/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/24/2021 Partial Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 10/12/2021 Corrections Issued DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 10/19/2021 Partial Approval DAVID SANDOVAL
BUILDING-Rough-Frame 10/29/2021 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 10/29/2021 Approved DAVID SANDOVAL
Green Building Rough 10/29/2021 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 10/29/2021 Corrections Issued DAVID SANDOVAL
MERV13>=Rough 10/29/2021 Approved DAVID SANDOVAL
PLUMBING-Rough 10/29/2021 Corrections Issued DAVID SANDOVAL
BUILDING-Rough-Frame 11/4/2021 Approved DAVID SANDOVAL
Gas Test 11/4/2021 Partial Inspection DAVID SANDOVAL
Green Building Rough 11/4/2021 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 11/4/2021 Approved DAVID SANDOVAL
PLUMBING-Rough 11/4/2021 Approved DAVID SANDOVAL
Shower Pan 11/4/2021 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 11/15/2021 Approved DAVID SANDOVAL
Green Building Rough 11/15/2021 Approved DAVID SANDOVAL
Insulation 11/19/2021 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/19/2021 Approved MORRIS JACKSON
Drywall Nailing 12/1/2021 Approved DAVID SANDOVAL