2752 W 14TH ST 90006
Certificate Information: 2752 W 14TH ST 90006
- Application / Permit
- 18014-20001-04733
- Plan Check / Job No.
- B19VN14300
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL PERMIT TO ADD ADDITIONAL FLOOR AREA (5'X19'5") TO INCREASE DINING/KITCHEN AREA & REVISE FLOOR PLAN.
- Permit Issued
- Issued on 1/14/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 6/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2019 | HAYATO TSUCHIYA |
| Corrections Issued | 8/26/2019 | HAYATO TSUCHIYA |
| Plan Check Approved | 1/6/2020 | HAYATO TSUCHIYA |
| Issued | 1/14/2020 | LADBS |
| Permit Finaled | 6/16/2021 | KATHRYN BUTTERWORTH |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/29/2019 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 8/29/2019 | STEVEN WECHSLER |
| Specific Plan | Cleared | 8/29/2019 | STEVEN WECHSLER |
| Green Code | Cleared | 9/10/2019 | HAYATO TSUCHIYA |
| HPOZ | Cleared | 9/24/2019 | AMANDA KAINER |
| Miscellaneous | Cleared | 9/24/2019 | AMANDA KAINER |
| Miscellaneous | Cleared | 9/24/2019 | AMANDA KAINER |
| Low Impact Development | Cleared | 10/11/2019 | JORGE MEJIA LEMUS |
| Hydrant and Access approval | Cleared | 1/3/2020 | GEORGE SUCHAND |
Contact Information
| Contractor | Pro Build Inc; Lic. No.: 1005294-B | 2321 1/2 S RIDGELEY DR LOS ANGELES, CA 90016 |
| Engineer | Wu,, Tzuoh-Jaw; Lic. No.: S5002 | 9352 LANGSTON ST RANCHO CUCAMONGA, CA 91730 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/30/2020 | Not Ready for Inspection | RICHARD STEINBACH |
| Footing/Foundation/Slab | 2/4/2020 | Not Ready for Inspection | HORACE FULTZ |
| Footing/Foundation/Slab | 2/14/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 3/24/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Underground Mechanical | 3/24/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Wood Frame | 3/24/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 7/1/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 7/1/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Rough-Elec/Plmb/HVAC | 7/1/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Sewer | 7/1/2020 | Approved | KATHRYN BUTTERWORTH |
| Underground Mechanical | 7/1/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 11/10/2020 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2020 | Approved | KATHRYN BUTTERWORTH |
| Gas Test | 11/10/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 11/10/2020 | Approved | KATHRYN BUTTERWORTH |
| Rough-Elec/Plmb/HVAC | 11/10/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 11/25/2020 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 11/25/2020 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 12/2/2020 | Approved | RICHARD STEINBACH |
| ELECTRICAL-Final | 6/7/2021 | Corrections Issued | SCOTT FINNILA |
| Final | 6/7/2021 | Partial Approval | SCOTT FINNILA |
| Green Building Final | 6/7/2021 | Approved | SCOTT FINNILA |
| HVAC-Final | 6/7/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 6/7/2021 | Corrections Issued | SCOTT FINNILA |
| Smoke Detectors | 6/7/2021 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 6/16/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 6/16/2021 | Permit Finaled | KATHRYN BUTTERWORTH |
| HVAC-Final | 6/16/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 6/16/2021 | Approved | KATHRYN BUTTERWORTH |