7252 N GLADE AVE 91303

Certificate Information: 7252 N GLADE AVE 91303

Application / Permit
18014-20001-02778
Plan Check / Job No.
B19VN14976
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL PERMIT OF 18014-20000-02778 TO CORRECT (E) GARAGE DIMENSIONS AND REVISE ADDITION TO IRREGULAR SHAPE 38'8" X 31.25'
Permit Issued
Issued on 9/9/2019
Issuing Office
Valley
Current Status
Permit Finaled on 10/15/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/5/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 ALDOUS CHIC
Corrections Issued 9/5/2019 ALDOUS CHIC
Plan Check Approved 9/9/2019 RARES BODEA
Issued 9/9/2019 LADBS
Permit Finaled 10/15/2020 DAVID STEPANYAN

Permit Application Clearance Information

Address approval Cleared 9/5/2019 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/5/2019 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 9/5/2019 GABRIEL ROBLES
Construction within easement Cleared 9/6/2019 OSCAR CASTRO

Contact Information

Contractor J L S Development Inc; Lic. No.: 919951-B 22054 WYANDOTTE ST      CANOGA PARK, CA 91303

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/12/2019 No Access for Inspection PETER FOLLING
Footing/Foundation/Slab 9/17/2019 Approved PETER FOLLING
PLUMBING-Rough 9/17/2019 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 11/15/2019 Not Ready for Inspection PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 11/15/2019 Approved PETER FOLLING
Green Building Rough 11/15/2019 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 12/12/2019 Approved PETER FOLLING
Gas Test 12/12/2019 Approved PETER FOLLING
Green Building Rough 12/12/2019 Not Ready for Inspection PETER FOLLING
HVAC-Rough 12/12/2019 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 12/12/2019 Not Ready for Inspection PETER FOLLING
Rough-Elec/Plmb/HVAC 12/12/2019 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 12/17/2019 Approved PETER FOLLING
Green Building Rough 12/17/2019 Approved PETER FOLLING
HVAC-Rough 12/17/2019 Approved PETER FOLLING
PLUMBING-Rough 12/17/2019 Approved PETER FOLLING
Insulation 12/24/2019 Approved PETER FOLLING
Drywall Nailing 1/2/2020 Approved RONALD COWAN
Interior/Exterior Lathing 1/2/2020 Approved RONALD COWAN
Shower Pan 3/25/2020 Approved HENRY KIM
ELECTRICAL-Final 9/2/2020 Corrections Issued DAVID STEPANYAN
Final 9/2/2020 Corrections Issued DAVID STEPANYAN
HVAC-Final 9/2/2020 Corrections Issued DAVID STEPANYAN
PLUMBING-Final 9/2/2020 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Final 9/14/2020 Not Ready for Inspection DAVID STEPANYAN
HVAC-Final 9/14/2020 Approved DAVID STEPANYAN
PLUMBING-Final 9/15/2020 Approved DAVID STEPANYAN