9153 W JANICE PL 90210
Certificate Information: 9153 W JANICE PL 90210
- Application / Permit
- 18014-20000-07323
- Plan Check / Job No.
- B18VN22152
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL TO (E) SINGLE FAMILY DWELLING. REMOVE 605 SQ FT OF (E) DWELLING AND REBUILD TO CONSTRUCT 80'-3" X 95'-5" FULLY SPRINKLERED SINGLE FAMILY DWELLING WITH ATTACHED 4-CAR GARAGE.
- Permit Issued
- Issued on 9/18/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2018 | APPLICANT |
| Green Plans Picked Up | 1/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 1/14/2019 | JEROME MAGAT PALMA |
| Quality Review Completed | 2/4/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 2/4/2019 | APPLICANT |
| Applicant returned to address corrections | 3/6/2019 | JEROME MAGAT PALMA |
| Plan Check Approved | 5/9/2019 | JEROME MAGAT PALMA |
| Issued | 9/18/2019 | LADBS |
| CofO in Progress | 1/12/2024 | RAUL BARAJAS |
| CofO Issued | 1/21/2024 | DEROLD HAUFF |
| Permit Finaled | 1/21/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/8/2019 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 2/8/2019 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 2/8/2019 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2019 | ADRIAN SANCHEZ |
| Permit | Cleared | 2/8/2019 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 2/8/2019 | ADRIAN SANCHEZ |
| Green Code | Cleared | 2/26/2019 | DAVID MATSON |
| Hydrant and Access approval | Cleared | 3/29/2019 | GEORGE SUCHAND |
| Miscellaneous | Cleared | 4/2/2019 | SHEILA GERSHON |
| Specific Plan | Cleared | 4/2/2019 | SHEILA GERSHON |
| ZI | Cleared | 4/2/2019 | SHEILA GERSHON |
| Low Impact Development | Cleared | 5/1/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/1/2019 | JEANETTE VONG |
| GPI Written Notices | Cleared | 5/9/2019 | BINH PHAN |
| Grading Pre-Inspection | Cleared | 5/9/2019 | BINH PHAN |
Contact Information
| Engineer | Hoffmayer,, Joseph Julian; Lic. No.: S3935 | 5043 EVANWOOD AVENUE OAK PARK, CA 91377 |
| Engineer | Walter,, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
| Geologist | Barrett,, Mark A; Lic. No.: EG2088 | 14428 HAMLIN ST 200 VAN NUYS, CA 91401 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/19/2020 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 8/25/2020 | No Access for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/22/2020 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 10/13/2020 | No Access for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 10/13/2020 | No Access for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 10/27/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/2/2020 | Partial Inspection | RAUL BARAJAS |
| Structural Steel Frame | 11/2/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Underground Mechanical | 11/10/2020 | Corrections Issued | DONALD CRICHLOW |
| PLUMBING-Rough | 1/14/2021 | Partial Approval | RAUL BARAJAS |
| HVAC-Rough | 10/8/2021 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 10/8/2021 | Partial Approval | RAUL BARAJAS |
| Wood Frame | 10/8/2021 | Partial Approval | RAUL BARAJAS |
| Drywall Nailing | 11/16/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 11/16/2021 | Approved | STUART CHAPMAN |
| Shower Pan | 3/18/2022 | No Access for Inspection | SCOTT FINNILA |
| Interior/Exterior Lathing | 4/4/2022 | Approved | RAUL BARAJAS |
| Shower Pan | 4/4/2022 | Approved | RAUL BARAJAS |
| Gas Test | 9/27/2022 | Partial Approval | RAUL BARAJAS |
| Pool Piping | 9/27/2022 | Partial Approval | RAUL BARAJAS |
| Sewer | 9/27/2022 | Partial Approval | RAUL BARAJAS |
| Service/Power Release | 12/5/2022 | Corrections Issued | RAUL BARAJAS |
| Enclosure/Fence | 1/27/2023 | Approved | RAUL BARAJAS |
| Service/Power Release | 1/27/2023 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 3/2/2023 | Conditional Approval | RAUL BARAJAS |
| Final | 3/2/2023 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/2/2023 | Approved | RAUL BARAJAS |
| Green Building Final | 3/2/2023 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 3/2/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 3/2/2023 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 3/2/2023 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 3/23/2023 | Approved | RAUL BARAJAS |
| Final | 3/23/2023 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 3/23/2023 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 3/23/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 3/23/2023 | Approved | RAUL BARAJAS |
| Final | 11/30/2023 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 11/30/2023 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Final | 12/13/2023 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | RAUL BARAJAS |
| Final | 1/16/2024 | OK to Issue CofO | RAUL BARAJAS |