11039 N PENDER AVE 91344
Certificate Information: 11039 N PENDER AVE 91344
- Application / Permit
- 18014-20000-07274
- Plan Check / Job No.
- B18VN22025
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE (E) 10' x 18' STORAGE. CONVERT 8' x 13' PORTION OF (E) GARAGE TO STORAGE, CONVERT REMAINING PORTION OF GARAGE AND ADD 18' x 40'-6" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 7/2/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/10/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2019 | JENNIFER LEE |
| Corrections Issued | 1/7/2019 | JENNIFER LEE |
| Applicant returned to address corrections | 6/14/2019 | ANGELICA DAVE |
| Plan Check Approved | 6/21/2019 | ANGELICA MARTINEZ |
| Issued | 7/2/2019 | LADBS |
| CofO in Progress | 7/20/2020 | JOHN JANSON |
| Permit Finaled | 11/10/2020 | JOHN JANSON |
| CofO Issued | 11/10/2020 | JOHN JANSON |
| Permit Finaled | 11/10/2020 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/24/2019 | RIDWAN HARDY |
| Address approval | Cleared | 6/14/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2019 | JOHN LIN |
| Sewer availability | Cleared | 6/14/2019 | JOHN LIN |
| Low Impact Development | Cleared | 6/21/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/21/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/18/2019 | Not Ready for Inspection | JOHN KIDWELL |
| Pre-Inspection | 8/15/2019 | Approved | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 8/28/2019 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 8/29/2019 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 8/29/2019 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2019 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 9/24/2019 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 9/24/2019 | Approved | DAVID SCANTLIN |
| Green Building Rough | 9/24/2019 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 9/24/2019 | Partial Approval | DAVID SCANTLIN |
| PLUMBING-Rough | 9/24/2019 | Approved | DAVID SCANTLIN |
| Sewer | 9/24/2019 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 9/26/2019 | Approved | SEAN WIRCH |
| Green Building Rough | 9/26/2019 | Approved | SEAN WIRCH |
| Insulation | 9/26/2019 | Approved | SEAN WIRCH |
| Drywall Nailing | 9/30/2019 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 10/1/2019 | Approved | DAVID SCANTLIN |
| Shower Pan | 10/1/2019 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 10/2/2019 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 10/17/2019 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 3/4/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Gas Test | 3/4/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Final | 3/4/2020 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 3/4/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 3/11/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 3/11/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 3/11/2020 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 3/11/2020 | Approved | DAVID SCANTLIN |
| Final | 7/16/2020 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 7/16/2020 | Approved | DAVID SCANTLIN |
| Service/Power Release | 7/16/2020 | Approved | DAVID SCANTLIN |