3245 N DREW ST 1-5 90065
Certificate Information: 3245 N DREW ST 1-5 90065
- Application / Permit
- 18014-20000-07163
- Plan Check / Job No.
- B18VN21639
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- INTERIOR AND EXTERIOR ARCHITECTURAL AND STRUCTURAL ALTERATIONS OF EXISTING APARTMENT BUILDING . ADDITION TO THE EXISTING APARTMENT AND THE GARAGE
- Permit Issued
- Issued on 11/2/2020
- Issuing Office
- Current Status
- CofO Issued on 1/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2018 | RUDOLF KINAR MELIKOFF |
| Corrections Issued | 1/2/2019 | RUDOLF KINAR MELIKOFF |
| Quality Review Completed | 1/3/2019 | STEVEN KIM |
| Building Plans Picked Up | 1/7/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 1/7/2019 | APPLICANT |
| Green Plans Picked Up | 1/7/2019 | APPLICANT |
| Applicant returned to address corrections | 3/11/2020 | RUDOLF KINAR MELIKOFF |
| Applicant returned to address corrections | 8/12/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 8/13/2020 | SALVADOR QUINTANILLA |
| Plan Check Approved | 10/6/2020 | SALVADOR QUINTANILLA |
| Issued | 11/2/2020 | APPLICANT |
| CofO in Progress | 1/27/2023 | RAFAEL CORTES |
| CofO Issued | 1/31/2023 | ERNESTO CORRAL |
| Permit Finaled | 1/31/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Green Code | Cleared | 5/10/2019 | PARISA ZAHABI |
| Address approval | Cleared | 5/13/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2019 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 5/13/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 5/13/2019 | LEE GUILBEAUX |
| DAS Clearance | Cleared | 5/22/2019 | NORLITO MEDRANO |
| Green Code | Cleared | 4/1/2020 | AARON COSTA |
| Supp. Use District POD/CDO/TDO | Cleared | 7/1/2020 | PABLO ESTRADA |
| ZA Case | Cleared | 7/1/2020 | PABLO ESTRADA |
| ZI | Cleared | 7/1/2020 | PABLO ESTRADA |
| Grading Pre-Inspection | Cleared | 8/19/2020 | RUDOLF KINAR MELIKOFF |
Contact Information
| Architect | Bond,, Dwight S; Lic. No.: C33276 | 1010 SYCAMORE AVENUE # 208 SOUTH PASADENA, CA 91030 |
| Contractor | Square One Construction Inc; Lic. No.: 1052077-B | 26512 GOLDFINCH PL SANTA CLARITA, CA 91351 |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 6541 ODESSA AVE UNIT 11 LAKE BALBOA, CA 91406 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/23/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Footing/Foundation/Slab | 11/30/2020 | Partial Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 1/21/2021 | Partial Approval | RONALD PACHECO |
| Structural Steel Frame | 1/21/2021 | Partial Approval | RONALD PACHECO |
| Green Building Rough | 3/1/2021 | Not Ready for Inspection | RONALD PACHECO |
| Wood Frame | 3/1/2021 | Not Ready for Inspection | RONALD PACHECO |
| Green Building Rough | 4/1/2021 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Pre-Inspection | 4/1/2021 | Approved | RUSSELL BONVOULOIR |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2021 | Partial Approval | RONALD PACHECO |
| Green Building Rough | 4/22/2021 | Not Ready for Inspection | RONALD PACHECO |
| Insulation | 4/22/2021 | Partial Approval | RONALD PACHECO |
| Wood Frame | 4/22/2021 | Partial Approval | RONALD PACHECO |
| Interior/Exterior Lathing | 9/8/2021 | Partial Approval | LANNY MERRICK |
| Interior/Exterior Lathing | 10/7/2021 | Partial Approval | MARK FERRARI |
| Green Building Rough | 11/23/2021 | Approved | MARK FERRARI |
| Wood Frame | 11/23/2021 | Partial Approval | MARK FERRARI |
| Insulation | 11/29/2021 | Approved | MARK FERRARI |
| Wood Frame | 11/29/2021 | Approved | MARK FERRARI |
| Drywall Nailing | 12/6/2021 | Approved | JONATHAN QUACH |
| Final | 9/28/2022 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 9/28/2022 | Approved | MARK FERRARI |
| Green Building Final | 9/28/2022 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 9/28/2022 | Approved | MARK FERRARI |
| Final | 1/26/2023 | OK to Issue CofO | RAFAEL CORTES |