848 N LACHMAN LANE 90272
Certificate Information: 848 N LACHMAN LANE 90272
- Application / Permit
- 18014-20000-07056
- Plan Check / Job No.
- B18VN21267
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 5'3" X 8'2" ADDITION TO (E) SFD TO CREATE A NEW FOYER, NEW 7'10" X 26'10" ADDITION TO (E) SFD TO ENLARGE THE KITCHEN AND LIVING ROOM , NEW 38'1/2" X 19'5-1/2" IRREGULAR SHAPED ADDITION TO (E) SFD TO CREATE MASTER BEDROOM , MASTER BATHROOM AND MASTER W.I.C. , NEW 12'2" X 13'7" , 6'2" X 26'10", 24'9" X 10', 6'6" X 22' REAR DECKS , INTERIOR REMODEL TO (E) SFD TO REMODEL BEDROOM # 3, BATHROOM #2, BATHROOM # 3, CREATE (2) CLOSETS , (1) NEW POWDER ROOM , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/3/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/11/2018 | APPLICANT |
| Green Plans Picked Up | 12/18/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2018 | RARES BODEA |
| Corrections Issued | 12/30/2018 | RARES BODEA |
| Quality Review Completed | 1/2/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 1/2/2019 | APPLICANT |
| Applicant returned to address corrections | 3/26/2019 | RARES BODEA |
| Plan Check Approved | 4/11/2019 | RARES BODEA |
| Issued | 5/3/2019 | LADBS |
| CofO in Progress | 8/18/2021 | ANDREW NAVE |
| Permit Finaled | 12/16/2021 | DANIEL ORRANTE |
| CofO Issued | 12/16/2021 | DANIEL ORRANTE |
| Permit Finaled | 12/16/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Green Code | Cleared | 1/24/2019 | PARISA ZAHABI |
| GPI Written Notices | Cleared | 3/26/2019 | RARES BODEA |
| Low Impact Development | Cleared | 3/29/2019 | MITESH PATEL |
| BHO/Hillside ordinance | Cleared | 4/3/2019 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 4/3/2019 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 4/3/2019 | HISASHI KOBAYAKAWA |
| Coastal Zone | Cleared | 4/3/2019 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2019 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 4/3/2019 | HISASHI KOBAYAKAWA |
| Construction near power lines | Cleared | 4/4/2019 | OSCAR CASTRO |
| Grading Pre-Inspection | Cleared | 4/5/2019 | SERGIO VALENZUELA |
| Distance to fire station | Cleared | 4/10/2019 | JOHN DALLAS |
| Hydrant and Access approval | Cleared | 4/10/2019 | JOHN DALLAS |
| Roof/Waste drainage to street | Cleared | 4/10/2019 | CHRISTOPHER LAW |
| Hold | Cleared | 6/20/2019 | LOURDES RAMIRO |
Contact Information
| Architect | Gemigniani,, Richard Louis; Lic. No.: C18783 | 14263 VALLEY VISTA BLVD. SHERMAN OAKS, CA 91403 |
| Contractor | Mp Construction Inc; Lic. No.: 1021054-B | 6923 GEYSER AVENUE RESEDA, CA 91335 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/7/2019 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 6/24/2019 | Partial Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 6/24/2019 | Partial Approval | ANDREW NAVE |
| HVAC-Rough | 6/24/2019 | No Access for Inspection | ANDREW NAVE |
| Piling/Pier/Caisson | 6/24/2019 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/28/2019 | Partial Approval | ANDREW NAVE |
| Piling/Pier/Caisson | 6/28/2019 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 7/1/2019 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 7/12/2019 | Corrections Issued | ANDREW NAVE |
| Special/Order Compliance | 7/15/2019 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 8/6/2019 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 8/13/2019 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 8/15/2019 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2019 | Partial Approval | ANDREW NAVE |
| Special/Order Compliance | 9/23/2019 | Partial Inspection | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 10/2/2019 | Not Ready for Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 10/8/2019 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2019 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 10/24/2019 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Rough | 11/26/2019 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2019 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Rough | 11/26/2019 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 11/26/2019 | Not Ready for Inspection | ANDREW NAVE |
| Green Building Rough | 12/3/2019 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 12/3/2019 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 12/4/2019 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2019 | Partial Approval | DANNY TOLENTINO |
| HVAC-Rough | 12/4/2019 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2019 | Partial Approval | ANDREW NAVE |
| Wood Frame | 12/10/2019 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 1/16/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 2/27/2020 | Not Ready for Inspection | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 3/2/2020 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2020 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2020 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2020 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Rough | 5/29/2020 | Approved | ANDREW NAVE |
| Gas Test | 5/29/2020 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Rough | 5/29/2020 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 5/29/2020 | Approved | ANDREW NAVE |
| Wood Frame | 5/29/2020 | Not Ready for Inspection | ANDREW NAVE |
| Wood Frame | 6/3/2020 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 6/10/2020 | Conditional Approval | ANDREW NAVE |
| Shower Pan | 6/10/2020 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 6/16/2020 | Approved | ANDREW NAVE |
| Insulation | 6/16/2020 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 6/16/2020 | Approved | ANDREW NAVE |
| Drywall Nailing | 6/19/2020 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/19/2020 | Approved | ANDREW NAVE |
| Green Building Rough | 6/19/2020 | Approved | ANDREW NAVE |
| Service/Power Release | 7/30/2020 | Not Ready for Inspection | ANDREW NAVE |
| Service/Power Release | 8/28/2020 | Not Ready for Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 8/31/2020 | Approved | ANDREW NAVE |
| Green Building Final | 8/31/2020 | No Access for Inspection | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 8/31/2020 | SGSOV Not Ready | ANDREW NAVE |
| Service/Power Release | 8/31/2020 | Not Ready for Inspection | ANDREW NAVE |
| Smoke Detectors | 8/31/2020 | No Access for Inspection | ANDREW NAVE |
| Service/Power Release | 9/3/2020 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 9/11/2020 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Final | 9/11/2020 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Final | 9/11/2020 | Not Ready for Inspection | ANDREW NAVE |
| Smoke Detectors | 9/11/2020 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 9/21/2020 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Final | 9/21/2020 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 10/19/2020 | Approved | ANDREW NAVE |
| HVAC-Final | 10/19/2020 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Final | 10/19/2020 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 10/19/2020 | Approved | ANDREW NAVE |
| Special/Order Compliance | 10/19/2020 | Corrections Issued | ANDREW NAVE |
| Special/Order Compliance | 11/19/2020 | Corrections Issued | ANDREW NAVE |
| Special/Order Compliance | 12/14/2020 | Partial Inspection | ANDREW NAVE |
| Final | 5/27/2021 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 5/27/2021 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 5/27/2021 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 5/27/2021 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 5/27/2021 | Approved | ANDREW NAVE |
| Final | 7/12/2021 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 7/12/2021 | Approved | ANDREW NAVE |
| HVAC-Final | 7/12/2021 | Approved | ANDREW NAVE |
| Final | 8/16/2021 | Not Ready for Inspection | ANDREW NAVE |
| Final | 8/18/2021 | OK to Issue CofO | ANDREW NAVE |