2041 S LINNINGTON AVE 90025
Certificate Information: 2041 S LINNINGTON AVE 90025
- Application / Permit
- 18014-20000-07016
- Plan Check / Job No.
- B18VN21154
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE 3'-0" X 18'-0" IRREGULAR PORTION OF DETACHED GARAGE, ADD 7'-9" X 8'-0" TO EXTEND (E) 1-CAR GARAGE TO REMAIN, CONVERT 8'-5" X 21'-0" IRREGULAR PORTION OF GARAGE AND ADD IRREGULAR 10'-4" X 30'-0" AT FIRST FLOOR AND NEW 23'-4" X 26'-9" SECOND FLOOR ADDITION FOR NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/21/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2018 | APPLICANT |
| Green Plans Picked Up | 12/18/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2018 | JENNIFER LEE |
| Corrections Issued | 12/26/2018 | JENNIFER LEE |
| Quality Review Completed | 12/27/2018 | STEVEN KIM |
| Building Plans Picked Up | 12/27/2018 | APPLICANT |
| Applicant returned to address corrections | 4/3/2019 | JENNIFER LEE |
| Plan Check Approved | 5/2/2019 | JENNIFER LEE |
| Issued | 5/21/2019 | LADBS |
| CofO in Progress | 10/28/2021 | BRENDAN LOONEY |
| Permit Finaled | 12/13/2021 | DANIEL ORRANTE |
| CofO Issued | 12/13/2021 | DANIEL ORRANTE |
| Permit Finaled | 12/13/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 2/25/2019 | APEKSHYA BAJRACHARYA |
| ZA Case | Cleared | 2/25/2019 | RICK TORRES |
| Green Code | Cleared | 3/19/2019 | DAVID MATSON |
| GPI Written Notices | Cleared | 4/3/2019 | JENNIFER LEE |
| Grading Pre-Inspection | Cleared | 4/3/2019 | JENNIFER LEE |
| Low Impact Development | Cleared | 4/30/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/2/2019 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shamsrad,, Shima; Lic. No.: C88470 | 6300 ORANGE STREET APT 3 LOS ANGELES, CA 90048 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/13/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 7/13/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 7/22/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Barrier | 7/22/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Subgrade | 7/22/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 7/22/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 8/19/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 10/20/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 10/28/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 10/28/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 10/28/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 10/28/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 1/20/2021 | Not Ready for Inspection | PIERRE VEGA |
| ELECTRICAL-Rough | 1/20/2021 | Approved | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2021 | Partial Approval | PIERRE VEGA |
| Gas Test | 1/20/2021 | Not Ready for Inspection | PIERRE VEGA |
| Green Building Rough | 1/20/2021 | Not Ready for Inspection | PIERRE VEGA |
| HVAC-Rough | 1/20/2021 | Not Ready for Inspection | PIERRE VEGA |
| METHANE-Rough | 1/20/2021 | Approved | PIERRE VEGA |
| PLUMBING-Rough | 1/20/2021 | Approved | PIERRE VEGA |
| Sewer | 1/20/2021 | Not Ready for Inspection | PIERRE VEGA |
| Underground Mechanical | 1/20/2021 | Not Ready for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 2/1/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 2/1/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 2/1/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 2/1/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 2/1/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 2/3/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 2/3/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Sewer | 2/3/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 2/3/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 2/12/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 2/12/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 2/12/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 2/12/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 2/12/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 2/17/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 2/17/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 2/17/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 3/1/2021 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/29/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 6/29/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 6/29/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 6/29/2021 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 7/20/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Final | 7/20/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 7/20/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 7/20/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 7/20/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 7/20/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 8/5/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 8/5/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 8/5/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 8/5/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 8/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 10/25/2021 | Conditional Approval | BRENDAN LOONEY |
| Final | 10/28/2021 | OK to Issue CofO | BRENDAN LOONEY |