11880 W LUCILE ST 90230
Certificate Information: 11880 W LUCILE ST 90230
- Application / Permit
- 18014-20000-06950
- Plan Check / Job No.
- B18VN20975
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION / MAJOR REMODEL TO SFD (1 OF 2)
- Permit Issued
- Issued on 1/30/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2018 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 12/21/2018 | VLADIMIR ARUTYUNYAN |
| Green Plans Picked Up | 12/21/2018 | APPLICANT |
| Quality Review Completed | 12/27/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 12/31/2018 | APPLICANT |
| Plan Check Approved | 1/30/2019 | VLADIMIR ARUTYUNYAN |
| Issued | 1/30/2019 | LADBS |
| CofO in Progress | 6/9/2025 | RUBEN RIVAS |
| CofO in Progress | 8/27/2025 | DAVID FEILER |
| Permit Finaled | 11/29/2025 | RICHARD STEINBACH |
| CofO Issued | 11/29/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/29/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Green Code | Cleared | 1/9/2019 | PARISA ZAHABI |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2019 | STEVE MELGAR |
| Low Impact Development | Cleared | 1/10/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/10/2019 | STEVE MELGAR |
| Sewer availability | Cleared | 1/10/2019 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Mohammad Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/26/2019 | Corrections Issued | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 3/13/2019 | Approved | TIM CHRISTENSEN |
| BUILDING-Rough-Frame | 3/26/2019 | Partial Approval | TIM CHRISTENSEN |
| Green Building Rough | 3/26/2019 | Not Ready for Inspection | TIM CHRISTENSEN |
| MERV13>=Rough | 3/26/2019 | Not Ready for Inspection | TIM CHRISTENSEN |
| PLUMBING-Rough | 3/26/2019 | Partial Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2019 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 4/3/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Rough | 4/3/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2019 | Partial Approval | TIM CHRISTENSEN |
| Green Building Rough | 4/18/2019 | Not Ready for Inspection | TIM CHRISTENSEN |
| MERV13>=Rough | 4/18/2019 | Not Ready for Inspection | TIM CHRISTENSEN |
| BUILDING-Rough-Frame | 5/9/2019 | Corrections Issued | KENNETH NAGLE |
| Interior/Exterior Lathing | 5/14/2019 | Approved | RONALD WEBER |
| BUILDING-Rough-Frame | 5/16/2019 | Corrections Issued | KENNETH NAGLE |
| ELECTRICAL-Rough | 5/16/2019 | Not Ready for Inspection | KENNETH NAGLE |
| HVAC-Rough | 5/16/2019 | Not Ready for Inspection | KENNETH NAGLE |
| MERV13>=Rough | 5/16/2019 | Not Ready for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 5/16/2019 | Not Ready for Inspection | KENNETH NAGLE |
| ELECTRICAL-Rough | 5/20/2019 | Approved | KENNETH NAGLE |
| HVAC-Rough | 5/20/2019 | Approved | KENNETH NAGLE |
| PLUMBING-Rough | 5/20/2019 | Partial Approval | KENNETH NAGLE |
| BUILDING-Rough-Frame | 5/22/2019 | Partial Approval | KENNETH NAGLE |
| Green Building Rough | 5/22/2019 | Approved | KENNETH NAGLE |
| Insulation | 5/22/2019 | Approved | KENNETH NAGLE |
| MERV13>=Rough | 5/22/2019 | Approved | KENNETH NAGLE |
| PLUMBING-Rough | 5/22/2019 | Approved | KENNETH NAGLE |
| Drywall Nailing | 5/29/2019 | Conditional Approval | KENNETH NAGLE |
| PLUMBING-Rough | 6/21/2019 | Approved | KENNETH NAGLE |
| Shower Pan | 6/21/2019 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 9/9/2019 | Not Ready for Inspection | KENNETH NAGLE |
| Final | 9/9/2019 | Not Ready for Inspection | KENNETH NAGLE |
| Green Building Final | 9/9/2019 | Not Ready for Inspection | KENNETH NAGLE |
| MERV13>=Final | 9/9/2019 | Not Ready for Inspection | KENNETH NAGLE |
| SGSOV-Seismic Gas S/O Valve | 9/9/2019 | SGSOV Not Ready | KENNETH NAGLE |
| Smoke Detectors | 9/9/2019 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 9/26/2019 | No Access for Inspection | KENNETH NAGLE |
| Final | 9/26/2019 | No Access for Inspection | KENNETH NAGLE |
| Green Building Final | 9/26/2019 | No Access for Inspection | KENNETH NAGLE |
| MERV13>=Final | 9/26/2019 | No Access for Inspection | KENNETH NAGLE |
| SGSOV-Seismic Gas S/O Valve | 9/26/2019 | SGSOV Not Ready | KENNETH NAGLE |
| BUILDING-Rough-Frame | 10/3/2019 | No Access for Inspection | KENNETH NAGLE |
| Final | 10/3/2019 | No Access for Inspection | KENNETH NAGLE |
| Green Building Final | 10/3/2019 | No Access for Inspection | KENNETH NAGLE |
| MERV13>=Final | 10/3/2019 | No Access for Inspection | KENNETH NAGLE |
| SGSOV-Seismic Gas S/O Valve | 10/3/2019 | SGSOV Not Ready | KENNETH NAGLE |
| Special/Order Compliance | 3/28/2025 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 4/10/2025 | Corrections Issued | RUBEN RIVAS |
| Final | 4/10/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 4/10/2025 | Approved | RUBEN RIVAS |
| MERV13>=Final | 4/10/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Not Ready | RUBEN RIVAS |
| BUILDING-Rough-Frame | 5/29/2025 | Approved | RUBEN RIVAS |
| Final | 5/29/2025 | Not Ready for Inspection | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 5/29/2025 | SGSOV Approved | RUBEN RIVAS |
| Special/Order Compliance | 8/29/2025 | Corrections Issued | DAVID FEILER |