905 N SERRANO AVE 90029
Certificate Information: 905 N SERRANO AVE 90029
- Application / Permit
- 18014-20000-06846
- Plan Check / Job No.
- B18VN20650
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- REMODEL OF (E) DUPLEX. ADDITION (10' X 6'-9") TO FIRST STORY. ADDITION (54'-10" X 35'-3" IRREGULAR SHAPE) OF SECOND STORY WITH CARPORT AND COVERED PATIO BELOW. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 10/11/2024
- Issuing Office
- Valley
- Current Status
- Issued on 10/11/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/3/2018 | APPLICANT |
| Green Plans Picked Up | 12/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2019 | ALYSSA N NARCISO |
| Corrections Issued | 1/8/2019 | ALYSSA N NARCISO |
| Quality Review Completed | 1/14/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 1/18/2019 | APPLICANT |
| Applicant returned to address corrections | 9/23/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 10/3/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 10/11/2024 | VAHAN JIVALAGIAN |
| Issued | 10/11/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/23/2019 | KARAN PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2019 | KARAN PATEL |
| Frnt yard landscape/Water mgmt | Cleared | 1/23/2019 | DIANA JIMENEZ |
| Housing rent stabilization | Cleared | 1/23/2019 | STEVEN HOFSTAD |
| Miscellaneous | Cleared | 1/23/2019 | DIANA JIMENEZ |
| Sewer availability | Cleared | 1/23/2019 | KARAN PATEL |
| Low Impact Development | Cleared | 9/17/2024 | MARCO SANCHEZ |
| Permit | Cleared | 9/17/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 9/17/2024 | WALLIE JONG |
Contact Information
| Contractor | 5 Blox Inc; Lic. No.: 1036356-B | 22287 MULHOLLAND HWY #176 CALABASAS, CA 91302 |
| Engineer | Vasquez,, Mario A; Lic. No.: C89006 | 1942 SPANISH BROOM DR PALMDALE, CA 93550 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/15/2025 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2025 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 6/9/2025 | Partial Inspection | JEFFREY MEAD |
| Underground Mechanical | 6/9/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2025 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 10/3/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 10/10/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 10/10/2025 | Approved | JEFFREY MEAD |
| Wood Frame | 11/3/2025 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 11/4/2025 | Approved | JEFFREY MEAD |
| Deputy Wood Construction | 11/4/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2025 | Approved | JEFFREY MEAD |
| Green Building Rough | 11/4/2025 | Approved | JEFFREY MEAD |
| MERV13>=Rough | 11/4/2025 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 11/4/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | JOSH MEISTER |
| Insulation | 11/14/2025 | Approved | JOSH MEISTER |
| Shower Pan | 11/14/2025 | Approved | JOSH MEISTER |
| Drywall Nailing | 11/20/2025 | Partial Inspection | JEFFREY MEAD |
| Interior/Exterior Lathing | 11/20/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Drywall Nailing | 11/21/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 11/21/2025 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 11/21/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 4/7/2026 | Approved | JOSH MEISTER |
| PLUMBING-Final | 4/7/2026 | Approved | JOSH MEISTER |
| HVAC-Final | 4/24/2026 | Corrections Issued | JEFFREY MEAD |
| Final | 5/1/2026 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 5/1/2026 | Approved | JEFFREY MEAD |
| Green Building Final | 5/1/2026 | Approved | JEFFREY MEAD |
| HVAC-Final | 5/1/2026 | Not Ready for Inspection | JEFFREY MEAD |
| MERV13>=Final | 5/1/2026 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 5/1/2026 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 5/1/2026 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 5/5/2026 | SGSOV Not Ready | JEFFREY MEAD |
| Final | 5/7/2026 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 5/7/2026 | Approved | JEFFREY MEAD |
| MERV13>=Final | 5/7/2026 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 5/7/2026 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 5/7/2026 | Approved | JEFFREY MEAD |