335 W 65TH ST 90003
Certificate Information: 335 W 65TH ST 90003
- Application / Permit
- 18014-20000-06675
- Plan Check / Job No.
- B18VN20098
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 3'-6" X 4'-0" ENTRY AT FIRST FLOOR AND 24'-2" X 39'-7" SECOND FLOOR ADDITION TO (E) SFD, REMODEL THROUGHOUT FIRST FLOOR. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/26/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2018 | JENNIFER LEE |
| Corrections Issued | 12/3/2018 | JENNIFER LEE |
| Quality Review Completed | 12/3/2018 | STEVEN KIM |
| Building Plans Picked Up | 12/3/2018 | APPLICANT |
| Green Plans Picked Up | 12/4/2018 | APPLICANT |
| Plan Check Approved | 12/14/2018 | JENNIFER LEE |
| Issued | 12/26/2018 | LADBS |
| CofO in Progress | 10/9/2020 | FREDDIE RIVERA |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
| CofO Issued | 3/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/4/2018 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2018 | RUDY TERRIQUEZ. |
| Green Code | Cleared | 12/5/2018 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 12/5/2018 | RUDY TERRIQUEZ. |
| Sewer availability | Cleared | 12/5/2018 | RUDY TERRIQUEZ. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/8/2019 | Partial Approval | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 1/22/2019 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2019 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2019 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2019 | Corrections Issued | FREDDIE RIVERA |
| Sewer | 5/28/2019 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2019 | Corrections Issued | BOB DUNN |
| ELECTRICAL-Rough | 11/22/2019 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 11/22/2019 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 11/22/2019 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 11/22/2019 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/2/2019 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 12/2/2019 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/19/2019 | Approved | EUGENE CASSIDY |
| Insulation | 1/22/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 1/31/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 1/31/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 1/31/2020 | Approved | EUGENE CASSIDY |
| Shower Pan | 1/31/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/18/2020 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/20/2020 | Corrections Issued | EUGENE CASSIDY |
| Pre-Inspection | 5/20/2020 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/27/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Drywall Nailing | 5/27/2020 | Approved | EUGENE CASSIDY |
| Final | 5/27/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 5/27/2020 | Corrections Issued | EUGENE CASSIDY |
| MERV13>=Final | 5/27/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Rough | 5/27/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/27/2020 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 5/27/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/30/2020 | Approved | EUGENE CASSIDY |
| Final | 6/30/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 6/30/2020 | Corrections Issued | EUGENE CASSIDY |
| MERV13>=Final | 6/30/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/30/2020 | SGSOV Approved | EUGENE CASSIDY |
| Final | 7/8/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/8/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 7/8/2020 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/23/2020 | Corrections Issued | JOSEPH MCGARRY |
| Final | 8/5/2020 | Corrections Issued | COREY HUPP |
| Green Building Final | 8/5/2020 | Not Ready for Inspection | COREY HUPP |
| Final | 9/28/2020 | No Access for Inspection | JOSEPH MCGARRY |
| Green Building Final | 9/28/2020 | No Access for Inspection | JOSEPH MCGARRY |
| Final | 10/6/2020 | Conditional Approval | FREDDIE RIVERA |
| Green Building Final | 10/6/2020 | Approved | FREDDIE RIVERA |